Difference between revisions of "Run Planning Meeting Notes, August 13 -17, 2020"
From GlueXWiki
(→Thursday, August 13) |
|||
Line 14: | Line 14: | ||
# Reports/Issues | # Reports/Issues | ||
#* Monitoring link (Twice a day monitoring line) is slow last night. [https://logbooks.jlab.org/entry/3826008] | #* Monitoring link (Twice a day monitoring line) is slow last night. [https://logbooks.jlab.org/entry/3826008] | ||
− | #* DIRC LV tripped due to the | + | #* DIRC LV tripped due to the current off during swing [https://logbooks.jlab.org/entry/3825890] |
# Run Plan | # Run Plan | ||
#* Next harp scan? | #* Next harp scan? |
Revision as of 08:26, 13 August 2020
<- Back to Run Coordination Meetings:Summer2020
Thursday, August 13
- Last 24 hours
- Unstable beam yesterday swing shift due to Hall C Moller measurement: 4:00-7:00 pm, 350nA tripping off AD00, unstable 240 nA available.
- Stable beam established after 7:30 pm yesterday.
- Diamond alignment completed by Hovanes during his shift
- TAGH scan completed by Sasha during his shift [1]
- Reports/Issues
- Run Plan
- Next harp scan?
- Production
- Hall C path change tentatively at August 24th (for three days). Impact initial 3 days of running without orbit lock (Hall A is off in the same time), 350nA beam will trip AD00.
- CPP installation:
- CPP's preference: schedule the CPP test after Aug 21.
- Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided.
- Report/test
- Pending issues:
- TagM card issue, any update?