(Thursday, August 13)
(Thursday, August 13)
Line 14: Line 14:
 
#* DIRC LV tripped due to the cur off during night
 
#* DIRC LV tripped due to the cur off during night
 
# Run Plan
 
# Run Plan
#* Production
+
#* Production  
#* Tuesday: Pass change for Hall C ?
+
#* Hall C path change tentatively at August 24th. Impact initial 3 days of running without orbit lock, 350nA beam will trip AD00.
 +
#* CPP installation:
 +
#** CPP's preference: schedule the CPP test after Aug 21.
 +
#** Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided.
 
# Pending issues:
 
# Pending issues:
#* TagM card
+
#* TagM card issue.

Revision as of 08:08, 13 August 2020

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet

Thursday, August 13

  1. Last 24 hours
    • Diamond alignment completed by Hovanes during his shift
    • TAGH scan completed by Sasha during his shift
  2. Reports/Issues
    • Monitoring link (Twice a day monitoring line) is slow last night.
    • DIRC LV tripped due to the cur off during night
  3. Run Plan
    • Production
    • Hall C path change tentatively at August 24th. Impact initial 3 days of running without orbit lock, 350nA beam will trip AD00.
    • CPP installation:
      • CPP's preference: schedule the CPP test after Aug 21.
      • Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided.
  4. Pending issues:
    • TagM card issue.