Thursday, August 13

  1. Last 24 hours


    • TagM card replacements (Richard, Nick, Chris) [1]
    • Test crystals installed [2]
    • Beam tuning throughout the night
    • 8pm: Harp scan attempt, motor stuck [3], [4], done at 10:30pm
    • 2:45am: Harp scan [5]
    • 6:00am: Production
  1. Reports/Issues
    • DIRC LV tripped due to the cur off during night
  1. Run Plan
    • Moving beam spot on diamond during Hovanes' shift
    • Production
    • Tuesday: Pass change for Hall C ?
  2. AOB
    • Thanks to all on-site and monitoring shift crews, experts on call and everybody working in the hall
    • Next RC: Bill Li