Run Planning Meeting Notes, August 13 -17, 2020

From GlueXWiki
Revision as of 07:49, 17 August 2020 by Billlee (Talk | contribs)

Jump to: navigation, search

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet




Friday, August 14

  1. Weekend Running
    • Since 20:00 Friday, we collected 8.5B triggers (~3.4B/day)
    • Beamline pump failed (8/15, 11am) 2nd time in 3 days, lost about 1 hour beam time.
    • CHL Trip (8/16, 8am) 6 hours down time.
    • Two Harp scan results:


  1. Reports/Issues
  1. Pending issues:
    • TagM cards being debugged
    • TAGH Disc counter not functioning properly



Friday, August 14

  1. Last 24 hours
    • Stable-ish beam through yesterday to this morning, ~1.3 B triggers collected
    • Beamline Turbo pump controller failed, Keith came in and fixed the issue. Lost 2 hour beam time [1] [2] Pump failing
  2. Reports/Issues
    • New 45/135 coherent peak edge Perp Para
      • 45/135 new spot is close to the diamond edge, we need to pay attention to the rate.
    • Need to pay special attention to the coherent peak position
      • Amount of adjust (to the coherent peak) is increased (45/135) each time we change orientation
      • Amo to 0/90 para requires (Beni)
    • Beam drift due to lost beam lock. [3]
    • Hodoscope disc [4]
    • Missing FCAL channels due to the lost communication FCAL controller last night this morning
  3. Pending issues:
    • TagM card issue:
    • FCAL remote controller PDU reset. (No reset planned for other three PDUs)
  4. Run Plan
    • No long beam trips, no harp yesterday. Next harp scan?
    • Production
    • Hall C path change tentatively at August 24th (for three days). Question regarding beam stability and maximum current is raised to Jay, being discussed amount experts. Possible solution: tune beam two a shift to stabilize the lock; Use AD00 BCM as BPM, etc. Jay will get back to me.
    • CPP installation:
      • CPP's preference: schedule the CPP test after Aug 21.
      • Maintenance schedule to be decided.

Thursday, August 13

  1. Announcement
  2. Last 24 hours
    • Unstable beam yesterday swing shift due to Hall C Moller measurement: 4:00-7:00 pm, 350nA tripping off AD00, unstable 240 nA available.
    • Stable beam established after 7:30 pm yesterday.
    • Diamond (JD-105 45/135) alignment completed by Hovanes during his shift
    • TAGH scan completed by Sasha during his shift [5]
  3. Reports/Issues
    • Monitoring link (Twice a day monitoring line) is slow last night. [6]
    • DIRC LV tripped due to the current off during swing [7]
  4. Run Plan
    • Next harp scan?
    • Production
    • Hall C path change tentatively at August 24th (for three days). Impact initial 3 days of running without orbit lock (Hall A is off in the same time), 350nA beam will trip AD00.
    • CPP installation:
      • CPP's preference: schedule the CPP test after Aug 21.
      • Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided.
  5. Report/test
  6. Pending issues:
    • TagM card issue, any update?