Run Planning Meeting Notes, August 3- August 10, 2022

From GlueXWiki
Revision as of 07:40, 5 August 2022 by Deurpam (Talk | contribs) (Friday August 5)

Jump to: navigation, search
Back to Run Coordination Meetings:Summer2022

Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs


Friday August 5

Past 24 hours

  • Running on empty target (60 nA).
  • Plan to do TAC run Thursday was postponed (Today, or around Aug. 15th).
  • Everything is going well: 15.1h of ABU (63% efficiency). Time loss mostly due to thunderstorm (3h).

Shift Reports

Reports

Issues

Plans

  • RF recovery until ~noon +/- 1h. Access to put back Pb target if no TAC run today?
  • TAC run in the afternoon ? (Thunderstorms forecast) or production on Pb.
  • Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive).

Thursday August 4

Past 24 hours

  • Running on empty target (60 nA). Everything is going nicely and smoothly: 16.6h of ABU (69% efficiency).

Shift Reports

Reports

Issues

Plans

  • Production running on empty target until Thursday
  • Thursday morning, TAC run starting ~9am? (7-8 hours, assuming stable beam)
  • RF Recovery for 4hrs on Friday to prepare for weekend. Starts at 7:15am.
  • Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive).