Difference between revisions of "Run Planning Meeting Notes, August 6 - 12, 2020"

From GlueXWiki
Jump to: navigation, search
(Friday, August 7)
(Friday, August 7)
Line 6: Line 6:
 
# Last 24 hours
 
# Last 24 hours
 
#* Diamond alignment check (Hovanes)
 
#* Diamond alignment check (Hovanes)
 +
#** Coherent edges are reproducible to about 20 MeV, tweaking may be necessary
 +
#** Add screen shots of the coherent edges to logbook
 +
#** "force para/perp" and "save as default" for each of the four settings
 
#* [https://logbooks.jlab.org/entry/3821523 Trigger check-out] (Sasha)
 
#* [https://logbooks.jlab.org/entry/3821523 Trigger check-out] (Sasha)
 
#* TagH and PS HV scan
 
#* TagH and PS HV scan

Revision as of 12:39, 6 August 2020

<- Back to Run Coordination Meetings:Fall2019 Run

Integrated trigger count

Friday, August 7

  1. Last 24 hours
    • Diamond alignment check (Hovanes)
      • Coherent edges are reproducible to about 20 MeV, tweaking may be necessary
      • Add screen shots of the coherent edges to logbook
      • "force para/perp" and "save as default" for each of the four settings
    • Trigger check-out (Sasha)
    • TagH and PS HV scan
  2. Reports/Issues
    • Remind MCC to put in dumplet when changing radiators
  3. Run Plan
    • Complete first production cycle with 350nA

Thursday, August 6

  1. Last 24 hours
    • 5th pass separator problems after thunderstorm in the evening
    • Beam recovered around midnight
    • Harp scan: results
    • Radiation levels checked: similar to spring
  2. Reports/Issues
  3. Run Plan
    • Diamond alignment (Hovanes)
    • Trigger, PS, TagH check (Sasha)
    • Pass change at noon