Difference between revisions of "Run Planning Meeting Notes, Dec 5-Dec 11, 2019"

From GlueXWiki
Jump to: navigation, search
(Friday, Dec 6 at 08:45)
(next meeting (hopefully Monday, Dec 9 at 08:45))
Line 13: Line 13:
  
 
== next meeting (hopefully Monday, Dec 9 at 08:45) ==
 
== next meeting (hopefully Monday, Dec 9 at 08:45) ==
# Friday morning's data-taking was curtailed by a radiation level problem which prevented MCC from delivering beam to any of the halls.  We are using this time for the many requested opportunistic access requests - Colin (rebooting FCAL's PDU), Hovanes (ComCAL), Scot (PS magnet), Beni (TOF), Nick(?).  Sasha expected at noon.
+
# Since Friday morning:
 +
#* Morning data-taking was curtailed by a radiation level problem which prevented MCC from delivering beam to any of the halls.  We are using this time for the many requested opportunistic access requests - Colin (rebooting FCAL's PDU), Hovanes (ComCAL), Scot (PS magnet), Beni (TOF), Nick(?).   
 +
#* Solenoid started ramping at 7am.
 +
#* Richard resumed PS uscope threshold scan piecemeal whenever he could, running independently
 +
#* Bill took some DIRC LED trigger data, also running independently
 +
#* Swing shift started CDC and TOF HV scans.
 +
# Plan for the weekend
 +
#* Continue DIRC commissioning overnight
 +
#* Saturday diamond alignment, then DIRC commissioning with diamond overnight
 +
#* Sunday David CPP test for 1h, otherwise DIRC commissioning
  
 
== Friday, Dec 6 at 08:45 ==
 
== Friday, Dec 6 at 08:45 ==

Revision as of 22:43, 6 December 2019

<- Back to Run Coordination Meetings:Fall2019 Run

next meeting (hopefully Monday, Dec 9 at 08:45)

  1. Since Friday morning:
    • Morning data-taking was curtailed by a radiation level problem which prevented MCC from delivering beam to any of the halls. We are using this time for the many requested opportunistic access requests - Colin (rebooting FCAL's PDU), Hovanes (ComCAL), Scot (PS magnet), Beni (TOF), Nick(?).
    • Solenoid started ramping at 7am.
    • Richard resumed PS uscope threshold scan piecemeal whenever he could, running independently
    • Bill took some DIRC LED trigger data, also running independently
    • Swing shift started CDC and TOF HV scans.
  2. Plan for the weekend
    • Continue DIRC commissioning overnight
    • Saturday diamond alignment, then DIRC commissioning with diamond overnight
    • Sunday David CPP test for 1h, otherwise DIRC commissioning

Friday, Dec 6 at 08:45

  1. Last 24h:
    • Now have enough straight track data for GEM at all 3 positions
    • GEM_TRD firmware updated between beam left and beam right running
    • FADC replaced on GEM_TRD. Readout issues with GEM_TRD (see Lubomir's logentry).
    • Richard started completing the uscope threshold scan ~6am ish - working on this until 11am. Busy (UConn) until 5pm.
    • Solenoid is ramping (Tim/Beni)
    • Hovanes disabled the alarms on two TAGH channels which have faulty HV boards
  2. Issues
  3. Reports
  4. Plan for today
    • Start solenoid ramping
    • Access at ~11 or when Richard finishes uscope scan
    • (Empty target before Richard does tagger accidentals measurement) (postpone these)
    • Fill target.
    • CDC & TOF scans
    • DIRC commissioning field-on
    • Opp access request from Sasha 30 mins to replace fcal fadcs, Nick, Colin, Beni...
  5. Plan for later
    • Reschedule tagger accidentals
    • Alexandre's comprehensive runplan now at #5
    • Spin dance likely Monday or Tuesday. We can have beam for some/most of this time.
    • Diamond alignment likely on Wednesday?
  6. Notes from this meeting.
    • Access at 11 for work as above
    • Alignment on Saturday as stable beam most likely
    • uscope threshold scan top priority
    • DIRC commissioning can use amo if necessary
    • try to reschedule tagger accidentals
    • No weekend meetings planned at present

Thursday, Dec 5 at 08:45

  1. Last 24h:
    • Straight tracks during the day, Justin & Sean working to debug recon and analyze the data
    • Sean got the general detector checkout done.
    • Sasha did the PS threshold scan and set up the PS trigger for Richard's uscope scan
    • Sasha set up trigger config for straight tracks excluding uscope so Richard can work independently
    • Richard's uscope scans half done, interrupted by ghost PSS button press from tagger hall, no beam from approx 9pm - 1am?
    • Lubomir's logentry
  2. Issues
    • Solenoid alarm
    • PSS fault
    • GEM cable or module swap
  3. Plan for today
    • After the meeting (TBD Justin), move GEM to position 2, fix electronics problem, then take more data until ~4pm?
    • Move GEM to position 3, then take more data until ~6am Friday?
  4. Plan for later
  5. Notes from this meeting.
    • Also need to check the GEM readout config
    • Beam time request from David for CPP
    • Radiation levels report from Alexandre
    • Repeated alarms for TAGH 151