Run Planning Meeting Notes, December 9 - December 15, 2021

From GlueXWiki
Revision as of 16:39, 8 December 2021 by Ssanties (Talk | contribs) (Created page with "[https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]<br> =Wednesday November 9= #Last 24h: #* Start counter dark rate test, Run 90454 [https://logbooks.jlab.org/entry...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

MCC whiteboard

Wednesday November 9

  1. Last 24h:
    • Start counter dark rate test, Run 90454 [1] (Beni)
    • 1 FCAL base changed [2] (Mark)
    • FADC replaced in the tagger crate[3] (Sasha)
    • PWO modules and lead scint glass installed in the PS setup [4] (Sasha)
  2. Issues
    • Hall D beam stopper cause almost four hours of down time [5] We recovered the beam at 15:20 pm. The biggest suspect is an air pressure issue that caused a "beam stopper stuck" fault within PLC. The cause needs further investigation.
  3. Plans
    • Beam Studies next Tuesday, Dec 14