(Thursday, Feb. 14 at 08:45)
Line 1: Line 1:
 
== Thursday, Feb. 14 at 08:45 ==
 
== Thursday, Feb. 14 at 08:45 ==
 
# Past 24 hours:
 
# Past 24 hours:
#* Beam profile:
+
#* Acceptable quality beam established early morning around 11:00 am.
 
+
#** Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506
#*DIRC data taking.
+
#* DIRC data taking.
 
+
 
# Issues
 
# Issues
#* Water Temperature
+
#* Cryo Water Temperature jump to 72F (limit 70F).
#* IOC lost comminication
+
#** Due to pump switch: https://logbooks.jlab.org/entry/3652512
#** IOCHDCOL
+
#* IOC lost communication
 +
#** IOCHDCOL failed at 21:30. Reported to us by MCC at 0:00. Reset at 1:50 am. Hovanes verified things are ok at 3am.  https://logbooks.jlab.org/entry/3652920
 
#* DIRC SSP problem:
 
#* DIRC SSP problem:
 
#** DAQ stopped twice due to the out of sync issue.
 
#** DAQ stopped twice due to the out of sync issue.
 
#* Tagger RF time:
 
#* Tagger RF time:
 
 
  
 
== Friday, Feb. 15 at 08:45 ==
 
== Friday, Feb. 15 at 08:45 ==

Revision as of 09:36, 14 February 2019

Thursday, Feb. 14 at 08:45

  1. Past 24 hours:
  2. Issues

Friday, Feb. 15 at 08:45