== Wednesday, Feb. 18 at 08:45 ==
+
 
 +
== Thursday, Feb. 14 at 08:45 ==
 +
# Past 24 hours:
 +
#* Acceptable quality beam established early morning around 11:00 am.
 +
#** Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506
 +
#* DIRC data taking.
 +
#*# DIRC analysis is on-going.
 +
# Issues
 +
#* Cryo Water Temperature jump to 72F (limit 70F).
 +
#** Due to pump switch: https://logbooks.jlab.org/entry/3652512
 +
#* IOC lost communication
 +
#** IOCHDCOL failed at 21:30. Reported to us by MCC at 0:00. Reset at 1:50 am. Hovanes verified things are ok at 3am.  https://logbooks.jlab.org/entry/3652920
 +
#* DIRC SSP problem:
 +
#** DAQ stopped twice due to the out of sync issue.
 +
#* Tagger RF time: https://logbooks.jlab.org/entry/3652533
 +
#* hdview2 is work working
 +
#Today:
 +
#* No planned access
 +
#* Opportunistic access requested by Kenoe to work on GEM.
 +
#* DIRC nominal running (MOROC threshold scan?)
 +
 
 +
 
 +
 
 +
== Friday, Feb. 15 at 08:45 ==
 +
# Past 24 hours:
 +
#* Nominal DIRC setting collected 1B triggers
 +
#** Switched to the higher MOROC threshold (200)
 +
#* Smooth overnight running at 180nA, coming back to the desired 225nA this morning.
 +
#* Both opportunistic accesses happened during the accelerator down time due to the bulk power supply failure.
 +
# Issues:
 +
#* Beam steered to the wrong BCM, therefore constrained the maximum beam delivered to 180nA
 +
#**Detailed log: https://logbooks.jlab.org/entry/3653554
 +
#* Goni camera, wrong angle, did something move? https://logbooks.jlab.org/entry/3653437
 +
#* root spy crash: https://logbooks.jlab.org/entry/3653678
 +
#* DIRC SSP
 +
#** Runs at MOROC threshold of 50 not possible due to the out of sync issue, need to be looked into
 +
#** Out of sync over night (after switching the MOROC threshold).
 +
#* hdview2 and monitoring email working?
 +
# Plan for today:
 +
#* keep collecting higher MOROC threshold data (up to 1B triggers).
 +
#* When beam is not available, 15 min LED runs with different pulsing and trigger conditions.
 +
#* No planned and opportunistic access
 +
 
 +
 
 +
 
 +
== Monday, Feb. 18 at 08:45 ==
 
# Over the weekend summary:
 
# Over the weekend summary:
 
#* Quote by Eugine: "All the problems landed on other ppl's court".
 
#* Quote by Eugine: "All the problems landed on other ppl's court".
 +
#** https://hallcweb.jlab.org/doc-public/ShowDocument?docid=1010
 
#* DIRC SSP firmware on Friday (thanks to Ben and Sasha)
 
#* DIRC SSP firmware on Friday (thanks to Ben and Sasha)
 
#* Low intensity program completed.
 
#* Low intensity program completed.
 
#* HV scan: two more settings remains  
 
#* HV scan: two more settings remains  
#* HI test on Sunday: for most of the day, we were the only hall up
+
#* HI test on Sunday: for most of the day, we were the only hall up.
 +
#** ToF inner layer off, DC HV reduced, Tpol excluded from the trigger.
 +
#** DIRC and DAQ passed the test!
 
#* Overnight: smooth 425nA scanning operation.
 
#* Overnight: smooth 425nA scanning operation.
 +
# Monitoring
 +
#* Only 6 out of 30 root monitoring plots are fully occupied.
 
# Plan for today:
 
# Plan for today:
 
#* Hall A, B and C are down, another HI test? @900nA?
 
#* Hall A, B and C are down, another HI test? @900nA?
 
# Issues:
 
# Issues:
 
#* hdview2: hang on the 1st event
 
#* hdview2: hang on the 1st event
#* DAQ: Randy factor cant be set.
+
#* DAQ: Randy factor cant be set and BCALroc.  
 
#* Any update on the RF issue?
 
#* Any update on the RF issue?
 
# Transition to the CPP
 
# Transition to the CPP
 +
 +
 +
== Tuesday, Feb. 19 at 08:45 ==
 +
# Past 24 hours
 +
#* 500 nA threshold scan: trigger rate 75k Hz
 +
#* Overnight: smooth 350nA scanning operation.
 +
#* HV scan: almost done, only few more settings remains
 +
# Data Analysis: https://logbooks.jlab.org/entry/3655915
 +
# Monitoring and rootspy:
 +
#* log from Dave: https://logbooks.jlab.org/entry/3655600
 +
#* log from Thomas: https://logbooks.jlab.org/entry/3655931
 +
# Plan for today:
 +
#* Complete HV scan and finish 350nA threshold scan.
 +
# Issues:
 +
#* Coherent peak degeneration:
 +
#** Feb 10: https://logbooks.jlab.org/entry/3650944
 +
#** Feb 19: https://logbooks.jlab.org/entry/3655872
 +
#* DAQ crash: rocDIRC, rocTAGMH and rocTRIG2 lost connection. Wouldn't come back after rebooting
 +
#* DIRC scalar implementation.
 +
#* Tagger cable swap: https://logbooks.jlab.org/entry/3653736
 +
# Hall access today:
 +
#* RF recovery for 8 hours.
 +
#* Mark, Colin and Beni. Restricted or not?
 +
#* Tagger Hall: restricted by 10 am for neutron detector work
 +
# Transition to the CPP
 +
#* Hall Access starting 7am tomorrow (Feb/19).
 +
#* Any running plan? ''As a matter of fact, [https://www.overleaf.com/read/yzzgqtddbfmy yes].''
 +
#* No RC meeting tomorrow.
 +
 +
 +
== Wednesday, Feb. 20 at 08:45 ==
 +
# DIRC commissioning completed, and DIRC crews are happy.
 +
# Issues:
 +
#* CSS unresponsive (5mins to open any new window): https://logbooks.jlab.org/entry/3656340
 +
#* RF problem found (Beni)
 +
#* Goniometer controller failed (Sunday afternoon) and replaced: https://logbooks.jlab.org/entry/3656044
 +
#** Coherent peak with 17um diamond: https://logbooks.jlab.org/entry/3656353
 +
#** Coherent peak with 47um diamond: https://logbooks.jlab.org/entry/3656361
 +
# CPP tasks and schedule:
 +
#* Revert back from the DIRC lumi settings (FDC, ToF, TAGM, TPol).
 +
#* Currently under restricted access til 12:00 pm, hall work on-going
 +
#* Lockup at noon (11:45am, MCC announcement).
 +
#* Radcon support arranged for 3-6pm
 +
# CPP run plan: https://www.overleaf.com/read/yzzgqtddbfmy
 +
# MCC whiteboard:
 +
#*[https://cebaf.jlab.org/files/ops/accboard/ MCC white board]
 +
#* We have priority today

Latest revision as of 07:19, 21 March 2019

Thursday, Feb. 14 at 08:45

  1. Past 24 hours:
  2. Issues
  3. Today:
    • No planned access
    • Opportunistic access requested by Kenoe to work on GEM.
    • DIRC nominal running (MOROC threshold scan?)


Friday, Feb. 15 at 08:45

  1. Past 24 hours:
    • Nominal DIRC setting collected 1B triggers
      • Switched to the higher MOROC threshold (200)
    • Smooth overnight running at 180nA, coming back to the desired 225nA this morning.
    • Both opportunistic accesses happened during the accelerator down time due to the bulk power supply failure.
  2. Issues:
  3. Plan for today:
    • keep collecting higher MOROC threshold data (up to 1B triggers).
    • When beam is not available, 15 min LED runs with different pulsing and trigger conditions.
    • No planned and opportunistic access


Monday, Feb. 18 at 08:45

  1. Over the weekend summary:
    • Quote by Eugine: "All the problems landed on other ppl's court".
    • DIRC SSP firmware on Friday (thanks to Ben and Sasha)
    • Low intensity program completed.
    • HV scan: two more settings remains
    • HI test on Sunday: for most of the day, we were the only hall up.
      • ToF inner layer off, DC HV reduced, Tpol excluded from the trigger.
      • DIRC and DAQ passed the test!
    • Overnight: smooth 425nA scanning operation.
  2. Monitoring
    • Only 6 out of 30 root monitoring plots are fully occupied.
  3. Plan for today:
    • Hall A, B and C are down, another HI test? @900nA?
  4. Issues:
    • hdview2: hang on the 1st event
    • DAQ: Randy factor cant be set and BCALroc.
    • Any update on the RF issue?
  5. Transition to the CPP


Tuesday, Feb. 19 at 08:45

  1. Past 24 hours
    • 500 nA threshold scan: trigger rate 75k Hz
    • Overnight: smooth 350nA scanning operation.
    • HV scan: almost done, only few more settings remains
  2. Data Analysis: https://logbooks.jlab.org/entry/3655915
  3. Monitoring and rootspy:
  4. Plan for today:
    • Complete HV scan and finish 350nA threshold scan.
  5. Issues:
  6. Hall access today:
    • RF recovery for 8 hours.
    • Mark, Colin and Beni. Restricted or not?
    • Tagger Hall: restricted by 10 am for neutron detector work
  7. Transition to the CPP
    • Hall Access starting 7am tomorrow (Feb/19).
    • Any running plan? As a matter of fact, yes.
    • No RC meeting tomorrow.


Wednesday, Feb. 20 at 08:45

  1. DIRC commissioning completed, and DIRC crews are happy.
  2. Issues:
  3. CPP tasks and schedule:
    • Revert back from the DIRC lumi settings (FDC, ToF, TAGM, TPol).
    • Currently under restricted access til 12:00 pm, hall work on-going
    • Lockup at noon (11:45am, MCC announcement).
    • Radcon support arranged for 3-6pm
  4. CPP run plan: https://www.overleaf.com/read/yzzgqtddbfmy
  5. MCC whiteboard: