Difference between revisions of "Run Planning Meeting Notes, Feb 15-Feb 21, 2018"
From GlueXWiki
(→Monday, February 19) |
(→Monday, February 19) |
||
Line 17: | Line 17: | ||
# Today's run plan [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Run Plan Google Calendar]: | # Today's run plan [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Run Plan Google Calendar]: | ||
#* Accelerator down for matching improvements & RF recovery (their estimate: 4-6hrs) | #* Accelerator down for matching improvements & RF recovery (their estimate: 4-6hrs) | ||
+ | #* Tuesday might also be an RF recovery day if it's not finished today | ||
#* Production | #* Production | ||
Revision as of 07:50, 19 February 2018
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Contents
Monday, February 19
- Notes from the previous 24 hours:
- Continued production data
- Issues:
- Reports (?):
- Intensity scan statistics
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Accelerator down for matching improvements & RF recovery (their estimate: 4-6hrs)
- Tuesday might also be an RF recovery day if it's not finished today
- Production
Sunday, February 18
- Notes from the previous 24 hours:
- Issues:
- Reports (?):
- Low level monitoring
- Intensity scan statistics
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Production
- Low intensity runs?
- More current scans?
- Other special runs?
Saturday, February 17
- Notes from the previous 24 hours:
- Accelerator delivered beam in the afternoon
- Collimator alignment scan completed
- Active collimator calibration scans
- Production data
- Issues:
- Reports (?):
- Intensity scan statistics
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Sasha's trigger tests
- Harp scan
- Empty target run
- Raw mode run while filling target
- Production
- Weekend meeting
- Sunday at 10:30am
Friday, February 16
- Notes from the previous 24 hours:
- Accelerator was down to restore the corners to values from a month ago
- Controlled Access
- Production data started around 2:30am
- Accelerator still having trouble delivering desired beam to all halls.
- Halls A and C are a factor of 3 lower in beam current
- Accelerator is discussing options which might involve beam going away (edit: Log entry discussing their plans)
- Issues:
- Reports (?):
- Intensity scan statistics
- Monitoring
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Ask for improvement in the harp scan
- Target studies by Chris Keith?
- Continue production data?
- Low intensity running?
- AC scans?
- Sasha trigger tests?
- Weekend meeting
- What day and time?
Thursday, February 15
- Notes from the previous 24 hours:
- Controlled Access
- Hovanes put lead on the beam profiler for the v-wire study
- Colin and Matt replaced FCAL bases
- Lubomir went in for the FDC
- (in the evening) Alex B. went in to swap voltage adapters for the active collimator
- Hovanes made a V-wire study
- Todd tried to improve beam optics but resulted in no change Rates
- Sergey and the DAQ group high intensity studies
- AC scan moved to later time with stable beam
- Intensity scan statistics
- Controlled Access
- Issues:
- Reports (?):
- Today's run plan Google Calendar:
- Accelerator down 4hr for "restoring corners" starting around 9am.
- Hall B Mott will be invasive, likely a couple hours without beam
- Controlled access during accelerator downtime
- Muon chamber work
- FCAL?
- Anyone else?
- Harp scan once beam returns
- AC scans
- Sasha trigger study