Difference between revisions of "Run Planning Meeting Notes, Feb 28 - Mar 6, 2019"

From GlueXWiki
Jump to: navigation, search
(Thursday, Feb. 28 at 08:45)
(Thursday, Feb. 28 at 08:45)
Line 10: Line 10:
 
# Past 24 hours:
 
# Past 24 hours:
 
#* Compton Production: ??? M triggers with Be
 
#* Compton Production: ??? M triggers with Be
 +
#* [https://logbooks.jlab.org/entry/3660887 Occupancy plots] - Sasha
 +
#* [https://logbooks.jlab.org/entry/3660842 Compton plots run 61322] - Drew
 
# Issues:
 
# Issues:
#* FYI: [https://logbooks.jlab.org/entry/3660650 Beam orbit locks off]
+
#* [https://logbooks.jlab.org/entry/3660650 Beam orbit locks off]
 +
#* [https://logbooks.jlab.org/entry/3660892 Unstable beam]
 
# Today (Thursday):
 
# Today (Thursday):
 
#* Remove Be foil @ 8 AM, but leave cylindrical holding tube.  Lockup hall at ~1 pm
 
#* Remove Be foil @ 8 AM, but leave cylindrical holding tube.  Lockup hall at ~1 pm

Revision as of 22:56, 27 February 2019



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Issues:
  3. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning?
  4. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  5. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Monday?