(Thursday, Feb. 28 at 08:45)
(Thursday, Feb. 28 at 08:45)
Line 9: Line 9:
 
== Thursday, Feb. 28 at 08:45 ==
 
== Thursday, Feb. 28 at 08:45 ==
 
# Past 24 hours:
 
# Past 24 hours:
#* [https://logbooks.jlab.org/entry/3660650 Beam orbit locks off]
+
#* [https://logbooks.jlab.org/entry/3660650 Beam orbit locks off] to allow Hall C current increase
 
#* [https://logbooks.jlab.org/entry/3660892 Unstable beam], lots of tuning to get high current for Hall A/C.  25 trips/hr average and will work to improve when they identify a path forward.
 
#* [https://logbooks.jlab.org/entry/3660892 Unstable beam], lots of tuning to get high current for Hall A/C.  25 trips/hr average and will work to improve when they identify a path forward.
 
#* Compton Production:  
 
#* Compton Production:  

Revision as of 09:31, 28 February 2019



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning?
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  4. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Monday?