(Thursday, Feb. 28 at 08:45)
(Thursday, Feb. 28 at 08:45)
Line 13: Line 13:
 
#* Compton Production:  
 
#* Compton Production:  
 
#** 2.86 billion triggers with Be ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61321&runTo=61344&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61321-61344])
 
#** 2.86 billion triggers with Be ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61321&runTo=61344&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61321-61344])
#** 0.24 billion triggers with no target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61308&runTo=61311&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61308-61311])
+
#** 0.24 billion triggers with previous no target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61308&runTo=61311&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61308-61311])
 
#* [https://logbooks.jlab.org/entry/3660887 Occupancy plots] - Sasha
 
#* [https://logbooks.jlab.org/entry/3660887 Occupancy plots] - Sasha
 
#* [https://logbooks.jlab.org/entry/3660842 Compton plot run 61322] - Drew
 
#* [https://logbooks.jlab.org/entry/3660842 Compton plot run 61322] - Drew

Revision as of 09:31, 28 February 2019



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning?
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  4. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Monday?