Difference between revisions of "Run Planning Meeting Notes, Feb 28 - Mar 6, 2019"

From GlueXWiki
Jump to: navigation, search
(Friday, Mar. 1 at 08:45)
(Friday, Mar. 1 at 08:45)
Line 27: Line 27:
 
# Past 24 hours:
 
# Past 24 hours:
 
#* [https://logbooks.jlab.org/entry/3661206 Examination of material in beamline]
 
#* [https://logbooks.jlab.org/entry/3661206 Examination of material in beamline]
 +
#* [https://logbooks.jlab.org/comment/20469#comment-20469 Shift in CompCal acceptance along +x]
 
#* Empty target production: ??? billion triggers with empty target (Runs ???-???)
 
#* Empty target production: ??? billion triggers with empty target (Runs ???-???)
 
# Today's plan:
 
# Today's plan:

Revision as of 13:58, 28 February 2019



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline

Friday, Mar. 1 at 08:45

  1. Past 24 hours:
  2. Today's plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  3. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?