Run Planning Meeting Notes, Feb 28 - Mar 6, 2019

From GlueXWiki
Revision as of 22:56, 27 February 2019 by Jrsteven (Talk | contribs) (Thursday, Feb. 28 at 08:45)

Jump to: navigation, search



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Issues:
  3. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning?
  4. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  5. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Monday?