Run Planning Meeting Notes, Feb 28 - Mar 6, 2019

From GlueXWiki
Revision as of 00:44, 1 March 2019 by Somov (Talk | contribs)

Jump to: navigation, search



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline

Friday, Mar. 1 at 08:45

  1. Past 24 hours:
  2. Today's plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline
      • Other work in the Hall: start counter installation, others?
  3. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?