Run Planning Meeting Notes, Feb 28 - Mar 6, 2019

From GlueXWiki
Revision as of 09:35, 1 March 2019 by Jrsteven (Talk | contribs) (Friday, Mar. 1 at 08:45)

Jump to: navigation, search



Thursday, Feb. 28 at 08:45

  1. Past 24 hours:
  2. Today (Thursday):
    • Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
    • Production running with no target until 6 am Friday morning
  3. Friday plan:
    • LHe target installation:
      • Hall open at 6 am for bleeding up beamline

Friday, Mar. 1 at 08:45

  1. Past 24 hours:
  2. Compton production statistics
    • 0.24 billion triggers with no target (Runs 61308-61311)
    • 2.86 billion triggers with Be (Runs 61321-61344)
    • 0.42 billion triggers with empty target holder cylinder (Runs 61345-61354)
    • Summary: Empty target is ~25% of statistics for Be target running
  3. Today's plan:
    • LHe target installation (ongoing):
      • Hall opened at 6 am for bleeding up beamline and target removal
      • Target installation ongoing and S&A to fiducialize and align target around 10 am
      • Other work in the Hall:
        • Start counter installation status: cabled and signals checked? who?
        • Others?
    • Empty (evacuated) LHe cell running overnight
  4. LHe target cooldown and filling schedule?
    • Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
    • Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?
  5. Plans for next week:
    • Beam studies on Monday:
      • Parity studies in Hall A from 8:30-12
      • Todd will work on improving Hall D optics and convergence from 12-4
    • RF recovery on Tuesday: expected but don't know duration yet