(Created page with "== Monday, Feb. 11 at 08:45 == # Notes from the past 72 hours: #* Beam restoration, system checkout and start of DIRC commissioning going well. #* Issues #**[https://logbooks....")
 
m (Monday, Feb. 11 at 08:45)
Line 6: Line 6:
 
#**[https://logbooks.jlab.org/entry/3650761 ], [https://logbooks.jlab.org/entry/3650010 ] DAQ lifetime sometimes drops]
 
#**[https://logbooks.jlab.org/entry/3650761 ], [https://logbooks.jlab.org/entry/3650010 ] DAQ lifetime sometimes drops]
 
#**TOF RF status?  
 
#**TOF RF status?  
 
 
#Today's plan
 
#Today's plan
 
#*8am: Hall D requested access during spin dance for Hall B.
 
#*8am: Hall D requested access during spin dance for Hall B.

Revision as of 08:22, 11 February 2019

Monday, Feb. 11 at 08:45

  1. Notes from the past 72 hours:
  2. Today's plan