Difference between revisions of "Run Planning Meeting Notes, February 16 - February 22, 2023"

From GlueXWiki
Jump to: navigation, search
(Shift Reports)
(Reports)
Line 23: Line 23:
  
 
=== Reports ===
 
=== Reports ===
* [https://logbooks.jlab.org/entry/4131000 Hall D survey] (Moser/RadCon)
+
* [https://logbooks.jlab.org/entry/4131747 Rebooting NMR meter and its IOC] (Hovanes)
 
* [https://logbooks.jlab.org/entry/4130972 CDC HVB current vs HV for 250nA HV scan runs on 4.5E-4RL Al on 17 Jan 2023] (Naomi)
 
* [https://logbooks.jlab.org/entry/4130972 CDC HVB current vs HV for 250nA HV scan runs on 4.5E-4RL Al on 17 Jan 2023] (Naomi)
 
* gluon100 rebooted PS/PSC scalers are visible (Sergey)
 
* gluon100 rebooted PS/PSC scalers are visible (Sergey)

Revision as of 08:24, 16 February 2023

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Thursday February 16

Past 24 hours

  • HARP scan results
  • No beam between 9am and 12am (beam came back at midnight)
  • CCAL transported to experimental hall and fixed to its platform by Scot and his team

Shift Reports

Reports

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM.

Plans

  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)