Difference between revisions of "Run Planning Meeting Notes, February 16 - February 22, 2023"

From GlueXWiki
Jump to: navigation, search
(Reports)
(Issues)
Line 34: Line 34:
 
=== Issues ===
 
=== Issues ===
 
* [https://logbooks.jlab.org/entry/4132216 A bad voltage board in the BCAL. Needs to be changed.] (Mark)
 
* [https://logbooks.jlab.org/entry/4132216 A bad voltage board in the BCAL. Needs to be changed.] (Mark)
 +
* [https://logbooks.jlab.org/entry/4132129 HallD Run #120726: LED ADC reference SiPM time anomaly]
 
Pending:
 
Pending:
 
* [https://logbooks.jlab.org/entry/4131558 TAGM discriminator TRG scaler gone wild]
 
* [https://logbooks.jlab.org/entry/4131558 TAGM discriminator TRG scaler gone wild]

Revision as of 09:44, 16 February 2023

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Thursday February 16

Past 24 hours

  • Production runs with a stable beam.
  • 2 BCAL HVs have been off since midnight due to a bad voltage board.

Shift Reports

Reports

Issues

Pending:

Plans

  • A bad BCAL HV board should be changed. Chris Stanislav is out today, and Mark D. is trying to find someone to change the BCAL board.
  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)