Run Planning Meeting Notes, February 16 - February 22, 2023

From GlueXWiki
Revision as of 17:23, 15 February 2023 by Keigo (Talk | contribs) (Thursday February 16)

Jump to: navigation, search

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Thursday February 16

Past 24 hours

  • HARP scan results
  • No beam between 9am and 12am (beam came back at midnight)
  • CCAL transported to experimental hall and fixed to its platform by Scot and his team

Shift Reports

Reports

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM.

Plans

  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)