Run Planning Meeting Notes, February 16 - February 22, 2023

From GlueXWiki
Revision as of 09:26, 20 February 2023 by Keigo (Talk | contribs) (Reports)

Jump to: navigation, search

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count

Monday February 20

Past 72 hours

  • Production runs. ABU = 35.5 h for the weekend. (12.7 h Friday, 13.8 h Saturday, 9.0 h Sunday)

Shift Reports Friday

Shift Reports Saturday

Shift Reports Sunday

Reports

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM. (~30 mins?)

Plans

  • BCM calibration from 10:00am (takes ~2h). Cannot access the hall during this task. Good time for BCAL cosmic runs?
  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Friday February 17

Past 24 hours

  • Mark D. replaced the bad BCAL HV board with a new one at 9:40am.
  • No beam from 13:00 to 17:30 (0L40 cryo issue). Several people worked in the hall during this downtime.
  • Production runs resumed after beam came back.

Shift Reports

Reports

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM. (~30 mins?)

Plans

  • On Monday, Sasha and Chris are planning to work in the hall (?)
  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)

Thursday February 16

Past 24 hours

  • Production runs with a stable beam.
  • 2 BCAL HVs have been off since midnight due to a bad voltage board.

Shift Reports

Reports

Issues

Pending:

Plans

  • A bad BCAL HV board should be changed. Chris Stanislav is out today, and Mark D. is trying to find someone to change the BCAL board.
  • Install CCAL whenever there is an extended accelerator downtime
    • Restricted Access is needed to be able to use the ramp <-done
    • Cabling
    • Survey is needed
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)