Difference between revisions of "Run Planning Meeting Notes, February 23 - February 28, 2023"
From GlueXWiki
(→Thursday February 23) |
(→Thursday February 23) |
||
Line 31: | Line 31: | ||
** Network port on the fan tray for FCAL11 crate is not working. When we have an expected long downtime, this tray should be replaced (Chris Stanislav). | ** Network port on the fan tray for FCAL11 crate is not working. When we have an expected long downtime, this tray should be replaced (Chris Stanislav). | ||
− | === Plans === | + | === Plans === |
+ | * Completion of CCAL installation | ||
+ | *Production (300 nA, 2h runs) with cycle: | ||
+ | **2 runs PARA (0/90) | ||
+ | **2 runs PERP (0/90) | ||
+ | **2 runs PARA (45/135) | ||
+ | **2 runs PERP (45/135) | ||
+ | **1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI) |
Revision as of 20:47, 22 February 2023
Zoom connect Meeting ID: 160 199 0060 / Passcode 8394
Hall D counting room white board
Contents
Thursday February 23
Past 24 hours
- Production runs
- Cosmic run in raw mode when beam was down: Run 120800
Shift Reports
Reports
Issues
Pending:
- Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
- TAGH hot channels w/ no beam
- Noise in FDC2 (Lubomir)
- FCAL11 crate problems (Sergey)
- Network port on the fan tray for FCAL11 crate is not working. When we have an expected long downtime, this tray should be replaced (Chris Stanislav).
Plans
- Completion of CCAL installation
- Production (300 nA, 2h runs) with cycle:
- 2 runs PARA (0/90)
- 2 runs PERP (0/90)
- 2 runs PARA (45/135)
- 2 runs PERP (45/135)
- 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)