Difference between revisions of "Run Planning Meeting Notes, February 23 - February 28, 2023"
From GlueXWiki
(→Shift Reports) |
(→Issues) |
||
Line 25: | Line 25: | ||
=== Issues === | === Issues === | ||
− | * Quality of coherent peak? Compare [https://logbooks.jlab.org/entry/4131776] from 2/15 and [https://logbooks.jlab.org/entry/4136910] from 2/22. | + | * Quality of coherent peak? Compare [https://logbooks.jlab.org/entry/4131776] from 2/15 and [https://logbooks.jlab.org/entry/4136910] from 2/22 and another for 45/135 perp: [https://logbooks.jlab.org/entry/4136947] |
*Pending: | *Pending: |
Revision as of 21:01, 22 February 2023
Zoom connect Meeting ID: 160 199 0060 / Passcode 8394
Hall D counting room white board
Contents
Thursday February 23
Past 24 hours
- Production runs
- Cosmic run in raw mode when beam was down: Run 120800
Shift Reports
Reports
Issues
- Pending:
- Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
- TAGH hot channels w/ no beam
- Noise in FDC2 (Lubomir)
- FCAL11 crate problems (Sergey)
Plans
- Completion of CCAL installation
- Production (300 nA, 2h runs) with cycle:
- 2 runs PARA (0/90)
- 2 runs PERP (0/90)
- 2 runs PARA (45/135)
- 2 runs PERP (45/135)
- 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)