Difference between revisions of "Run Planning Meeting Notes, February 2 - February 9, 2023"

From GlueXWiki
Jump to: navigation, search
Line 8: Line 8:
  
 
[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2023-01/index.html Integrated Trigger Count]
 
[https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2023-01/index.html Integrated Trigger Count]
 +
 +
 +
= Thursday February 5 =
 +
 +
=== Past 72 hours ===
 +
* Recovery from maintenance day. A couple of production runs. PSPEC troubleshooting. Test runs. 
 +
* ABU ~11.2h based on Beni's text messages.
 +
 +
=== Shift Reports ===
 +
====Friday====
 +
* [https://logbooks.jlab.org/entry/4123459 Day shift summary]
 +
* [https://logbooks.jlab.org/entry/4123652 Swing shift summary]
 +
* [https://logbooks.jlab.org/entry/4123818 Owl shift summary]
 +
* [https://logbooks.jlab.org/entry/4124047 Early Riser shift summary]
 +
====Saturday====
 +
* [https://logbooks.jlab.org/entry/4124228 Day shift summary]
 +
 +
 +
 +
=== Reports ===
 +
* [https://logbooks.jlab.org/entry/4122571 Power supply trip] (Tim, Scot).
 +
* [https://logbooks.jlab.org/entry/4122910 PS magnet at 800A] (Eugene).
 +
* [https://logbooks.jlab.org/entry/4122780 ALERT to shift leader: two TAGM columns still at operating Vbias] (Richard).
 +
* [https://logbooks.jlab.org/entry/4122719 Current scan to 950nA] (Lubomir)
 +
* [https://logbooks.jlab.org/entry/4123280 PSPEC current scan] (Sasha)
 +
 +
 +
*GlueX Statistics
 +
**PARA 0/90: 16=17%
 +
**PERP 0/90: 19%
 +
**PARA 45/135: 20%
 +
**PERP 45/135: 19%
 +
**AMO : 25%
 +
 +
=== Issues ===
 +
* [https://logbooks.jlab.org/entry/4122848 Pair Spec Magnet Power Supply Flush in morning (Tim)] We need to get PSPEC working at 1200Amps. 
 +
* [https://logbooks.jlab.org/entry/4123248 Issues with the TAGH HV module (Sasha)] Need to check this board again.
 +
* [https://logbooks.jlab.org/entry/4117764 Start Counter (Beni)] We want to confirm that the cables are in the right location.
 +
 +
 +
Pending:
 +
* BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.
 +
 +
=== Plans ===
 +
* Citra flush PSPEC power supply. Go to beam permit today.
 +
* Run production over weekend.
 +
* High current test with RADCON on Monday
 +
* RF recovery on Tuesday. Try to raise Hall A & C currents on Wednesday and possibly Thursday. 
 +
* Production (300 nA, 2h runs) with cycle:
 +
**2 runs para(0/90)
 +
**2 runs perp(0/90)
 +
**2 runs para(45/135)
 +
**2 runs perp(45/135)
 +
**1 run amo (use it to rejuvenate amo reference in CBREM GUI)
 +
  
  

Revision as of 21:24, 5 February 2023

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count


Thursday February 5

Past 72 hours

  • Recovery from maintenance day. A couple of production runs. PSPEC troubleshooting. Test runs.
  • ABU ~11.2h based on Beni's text messages.

Shift Reports

Friday

Saturday


Reports


  • GlueX Statistics
    • PARA 0/90: 16=17%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 19%
    • AMO : 25%

Issues


Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Citra flush PSPEC power supply. Go to beam permit today.
  • Run production over weekend.
  • High current test with RADCON on Monday
  • RF recovery on Tuesday. Try to raise Hall A & C currents on Wednesday and possibly Thursday.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)



Thursday February 3

Past 24 hours

  • Recovery from maintenance day. A couple of production runs. PSPEC troubleshooting. Test runs.
  • ABU ~11.2h based on Beni's text messages.

Shift Reports

Reports


  • GlueX Statistics
    • PARA 0/90: 16%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 19%
    • AMO : 25%

Issues


Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Citra flush PSPEC power supply. Go to beam permit today.
  • Run production over weekend.
  • High current test with RADCON on Monday
  • RF recovery on Tuesday. Try to raise Hall A & C currents on Wednesday and possibly Thursday.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)

Thursday February 2

Past 24 hours

  • Maintenance day, tour of Hall D by EIC review people. Beam is back at midnight.
  • Harp scans look OK [1]
  • Production on diamond. ABU= 2.9h for the day.

Shift Reports

Reports


  • GlueX Statistics
    • PARA 0/90: 16%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 18%
    • AMO : 25%

Issues

Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Wait for stable beam delivery for 4 halls. No timelime can be given.
  • CDC & FDC response studies at high luminosities. May not happen today, depends on 1uA beam delivery to Hall D.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)