Run Planning Meeting Notes, February 2 - February 9, 2023

From GlueXWiki
Revision as of 09:25, 3 February 2023 by Hovanes (Talk | contribs) (Past 24 hours)

Jump to: navigation, search

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count


Thursday February 3

Past 24 hours

  • Recovery from maintenance day. A couple of production runs. PSPEC troubleshooting. Test runs.
  • ABU ~11.2h based on Beni's text messages.

Shift Reports

Reports


  • GlueX Statistics
    • PARA 0/90: 16%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 19%
    • AMO : 25%

Issues

Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Citra flush PSPEC power supply. Go to beam permit today.
  • Run production over weekend.
  • High current test with RADCON on Monday
  • RF recovery on Tuesday. Try to raise Hall A & C currents on Wednesday and possibly Thursday.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)

Thursday February 2

Past 24 hours

  • Maintenance day, tour of Hall D by EIC review people. Beam is back at midnight.
  • Harp scans look OK [1]
  • Production on diamond. ABU= 2.9h for the day.

Shift Reports

Reports


  • GlueX Statistics
    • PARA 0/90: 16%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 18%
    • AMO : 25%

Issues

Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Wait for stable beam delivery for 4 halls. No timelime can be given.
  • CDC & FDC response studies at high luminosities. May not happen today, depends on 1uA beam delivery to Hall D.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)




Thursday February 3

Past 24 hours

  • Recovery from maintenance day. PSPEC troubleshooting. Test runs.


Shift Reports

Reports


  • GlueX Statistics
    • PARA 0/90: 16%
    • PERP 0/90: 19%
    • PARA 45/135: 20%
    • PERP 45/135: 18%
    • AMO : 25%

Issues

Pending:

  • BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period. PD will keep in contact with us on how to proceed.

Plans

  • Citra flush PSPEC power supply.
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)