Difference between revisions of "Run Planning Meeting Notes, February 9 - February 15, 2023"

From GlueXWiki
Jump to: navigation, search
(Past 24 hours)
(Wednesday February 9)
Line 17: Line 17:
 
* HARP scans
 
* HARP scans
 
** [https://logbooks.jlab.org/entry/4126952 HarpFitter:IHA5C11]
 
** [https://logbooks.jlab.org/entry/4126952 HarpFitter:IHA5C11]
 +
** []
 +
** []
  
 
=== Shift Reports ===
 
=== Shift Reports ===

Revision as of 23:51, 8 February 2023

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count


Wednesday February 9

Past 24 hours

Shift Reports

Reports

  • Statistics balance
    • PARA 0/90: 19%
    • PERP 0/90: 19%
    • PARA 45/135: 21%
    • PERP 45/135: 18%
    • AMO : 24%

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM.

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)