(Friday, January 17 at 08:45)
(Friday, January 17 at 08:45)
Line 27: Line 27:
 
#* Accidental study (Richard), 1 pm. 2100 nA beam, most HVs will be turned off, empty target. RadCon will monitor. [https://halldweb.jlab.org/wiki/index.php/Tagger_accidentals_rate_scan,_Fall_2019 Richard's proposal]
 
#* Accidental study (Richard), 1 pm. 2100 nA beam, most HVs will be turned off, empty target. RadCon will monitor. [https://halldweb.jlab.org/wiki/index.php/Tagger_accidentals_rate_scan,_Fall_2019 Richard's proposal]
 
#* Empty target run (2 hr)
 
#* Empty target run (2 hr)
 +
#* 30 min runs at 250 and 350 nA? To check number of rho, omegas / trigger. All subsystems ready?
 
# Plan for later
 
# Plan for later
 
#* Happy three day weekend! 🙂 Production data. No studies or downtime planned until Tuesday.
 
#* Happy three day weekend! 🙂 Production data. No studies or downtime planned until Tuesday.
 
#* Next meeting: Tuesday
 
#* Next meeting: Tuesday

Revision as of 20:36, 16 January 2020

Thursday, January 16 at 08:45

  1. Last 24 hours
    • Trippy beam yesterday and overnight. Issues in two cryomodules.
    • Some production data was collected.
    • L1 triggers studies have been postponed to today.
  2. Issues
    • Major bleed through, presumably from Hall A 1-pass beam 3764868
  3. Tasks for today
    • After spin dance (11 am -3 pm in accelerator plan): L1 triggers studies (Sasha, Beni, Justin)
    • Followed by cDAQ test (Sergey)
    • Production data otherwise
  4. Plan for later
    • Tagger accidental study (Richard). Tomorrow early a.m.? Will contact RadCon for final ok. Richard's proposal
    • Empty target run (target will already be emptied for accidental study).
    • Discussion of 24 GeV physics came up, physics ideas are welcome.

Friday, January 17 at 08:45

  1. Last 24 hours
    • High rate scan [1]
    • cDAQ
    • TOF thresholds
  2. Issues
  3. Tasks for today
    • Production data taking
    • RF recovery starting at 9 am
    • Accidental study (Richard), 1 pm. 2100 nA beam, most HVs will be turned off, empty target. RadCon will monitor. Richard's proposal
    • Empty target run (2 hr)
    • 30 min runs at 250 and 350 nA? To check number of rho, omegas / trigger. All subsystems ready?
  4. Plan for later
    • Happy three day weekend! 🙂 Production data. No studies or downtime planned until Tuesday.
    • Next meeting: Tuesday