Line 14: Line 14:
 
#* Empty target run (target will already be emptied for accidental study).
 
#* Empty target run (target will already be emptied for accidental study).
 
#* Discussion of 24 GeV physics came up, physics ideas are welcome.
 
#* Discussion of 24 GeV physics came up, physics ideas are welcome.
 +
 +
== Friday, January 17 at 08:45 ==
 +
# Last 24 hours
 +
# Issues
 +
#* Major bleed through
 +
# Tasks for today
 +
#* Production data taking
 +
#* RF recovery starting at 9 am
 +
#* Accidental study (Richard), 1 pm. Most HVs will be turned off. RadCon will monitor. [https://halldweb.jlab.org/wiki/index.php/Tagger_accidentals_rate_scan,_Fall_2019 Richard's proposal]
 +
#* Empty target run (2 hr)
 +
# Plan for later
 +
#* Happy three day weekend! 🙂 Production data taking, no downtime planned until Tuesday.

Revision as of 17:29, 16 January 2020

Thursday, January 16 at 08:45

  1. Last 24 hours
    • Trippy beam yesterday and overnight. Issues in two cryomodules.
    • Some production data was collected.
    • L1 triggers studies have been postponed to today.
  2. Issues
    • Major bleed through, presumably from Hall A 1-pass beam 3764868
  3. Tasks for today
    • After spin dance (11 am -3 pm in accelerator plan): L1 triggers studies (Sasha, Beni, Justin)
    • Followed by cDAQ test (Sergey)
    • Production data otherwise
  4. Plan for later
    • Tagger accidental study (Richard). Tomorrow early a.m.? Will contact RadCon for final ok. Richard's proposal
    • Empty target run (target will already be emptied for accidental study).
    • Discussion of 24 GeV physics came up, physics ideas are welcome.

Friday, January 17 at 08:45

  1. Last 24 hours
  2. Issues
    • Major bleed through
  3. Tasks for today
    • Production data taking
    • RF recovery starting at 9 am
    • Accidental study (Richard), 1 pm. Most HVs will be turned off. RadCon will monitor. Richard's proposal
    • Empty target run (2 hr)
  4. Plan for later
    • Happy three day weekend! 🙂 Production data taking, no downtime planned until Tuesday.