Run Planning Meeting Notes, Jan 16-Jan 22, 2020

From GlueXWiki
Revision as of 11:05, 16 January 2020 by Jzarling (Talk | contribs)

Jump to: navigation, search

Maintained primarily by RC for this week (Jon Z.). Other additions welcome.

Thursday, January 16 at 08:45

  1. Last 24 hours
    • Trippy beam yesterday and overnight. Some production data was collected.
    • L1 triggers studies (Sasha, Beni, Justin) have been postponed to today.
  2. Issues
    • Major bleed through, presumably from Hall A 1-pass beam 3764868
  3. Tasks for today
    • After spin dance (3 pm in accelerator plan): L1 triggers studies
    • Followed by cDAQ test
    • Production data otherwise
  4. Plan for later
    • Tagger accidental study (Richard). Tomorrow early a.m.? Will contact RadCon for final ok.

Misc. Notes

  1. MCC would like to perform a spin dance study for other halls Friday morning. This means four hours of beam studies time, during which hall D may or may not receive beam.