Run Planning Meeting Notes, Jan 25-Jan 31, 2018

From GlueXWiki
Revision as of 08:03, 25 January 2018 by Ostrov (Talk | contribs) (Created page with "<- Back to Run Coordination Meetings:Fall 2017 Spring 2018 Run ==Thursday, January 25 == # Notes from the previous 24 hrs: #* Beam was off from 9am till 5:20 pm. At the...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

<- Back to Run Coordination Meetings:Fall 2017 Spring 2018 Run

Thursday, January 25

  1. Notes from the previous 24 hrs:
    • Beam was off from 9am till 5:20 pm. At the end, Hall A was able to get their 22.5 uA current. Since then, beam was relatively stable.
    • Upon return of the beam, a harp scan was performed: MCC and Our harp. Beam seems to be acceptable.
    • After harp scan, about an hour has been spent on trigger and DAQ studies by Sasha and Sergei.
    • We switched to production running at 7pm and has been taking production data since then.
  2. Issues:
    • A couple of hours of beam time has been lost on fighting with DAQ while starting the next run (java out of memory, rebooting rocks, etc.)


    • Hall D switched from zero crossing to RF extracted [1] [2]
    • No downtime incidents of more than 30 minutes after 8 hrs of beam studies
    • Harp scans: 5C11(MCC), 5C11B(MCC), Radiator
      • (Sigma_X,Sigma_Y) for this scan: (1.10, 0.39), (0.87, 0.20), (0.76, 0.12)