==    Wednesday, February 5 ==  
 
==    Wednesday, February 5 ==  
 
# Last 24 hours
 
# Last 24 hours
 +
#* After RF separator and network issues yesterday morning, a good beam returned at 9:30am.
 +
#* No beam 2:30pm-6:30pm (two vacuum pump failures) [https://logbooks.jlab.org/entry/3777522], [https://logbooks.jlab.org/entry/3777584], [https://logbooks.jlab.org/entry/3777610], [https://logbooks.jlab.org/entry/3777640], [https://logbooks.jlab.org/entry/3777656]
 +
#* HOSS restarted at 6am [https://logbooks.jlab.org/entry/3777810]
 +
#* Production: 3.0B triggers.
 
# Issues
 
# Issues
 +
#* The last spare turbo pump [https://logbooks.jlab.org/entry/3777584]
 +
#* Easy recovery for the frozen gluon05 didn't work and led to hard reboot. [https://logbooks.jlab.org/entry/3777580]
 +
#* Noisy hodoscope channel [https://logbooks.jlab.org/entry/3777675]
 +
#* HV on FDC:hv:3:c4:4p had to be lowered.
 +
#* BTA from 4pm to 6:30pm: is it BANU or BNA? [https://logbooks.jlab.org/entry/3777801]
 
# Reports
 
# Reports
 
# Plans for today
 
# Plans for today
 +
#* Maintenance day until ~2pm, including 2hrs of NL access - a good opportunity for opportunistic access.
 +
#* Harp scan
 +
#* Production
  
 
==    Tuesday, February 4 ==  
 
==    Tuesday, February 4 ==  
 
# Last 24 hours
 
# Last 24 hours
 +
#* No beam:  11pm - 2:30am (beam tunning)
 +
#* Bad beam: since 5am - unstable and shifted by 3mm at AC (5th path separator issues).
 +
#* 9:30am: The latest harp scan [https://logbooks.jlab.org/entry/3776740]
 +
#* About 3.2B production triggers.
 +
# Changes
 +
#* 2pm: Same AMO reference in RootSpy as in cohbream gui [https://logbooks.jlab.org/entry/3776802]
 +
#* 4pm: A change in the data-taking procedure [https://logbooks.jlab.org/entry/3776904]:
 +
#** MCC should insert a dumplette before each no-beam goniometer movement
 +
#** Two production runs in a row for each radiator configuration.
 
# Issues
 
# Issues
 +
#* Display dumplette location on goniometer GUI
 +
#* Problems with coherent peak at the start of the swing shift. [https://logbooks.jlab.org/entry/3776891],[https://logbooks.jlab.org/entry/3776889]
 +
#* At 8pm, a number of IOC and DAQ stopped working for about 10 minutes. A network glitch is suspected. [https://logbooks.jlab.org/entry/3777013]
 +
#* Issue with EPICS archiving [https://logbooks.jlab.org/entry/3777282]
 
# Reports
 
# Reports
 +
#* Ratio of rates from HOSS [https://logbooks.jlab.org/entry/3776812]
 +
#* More on ratio of rates [https://logbooks.jlab.org/entry/3777287]
 +
#* Drifting beam energy [https://logbooks.jlab.org/entry/3777293]
 
# Plans for today
 
# Plans for today
 +
#* Production, production and more production.
  
 
==    Monday, February 3 ==  
 
==    Monday, February 3 ==  
Line 24: Line 53:
 
#** Goniometer stopped moving sometime between 5am and 3pm. The problem was only noticed at 3pm [https://logbooks.jlab.org/entry/3775465]. As a result, a few runs have unknown diamond orientation [https://logbooks.jlab.org/entry/3775587],[https://logbooks.jlab.org/entry/3775590]
 
#** Goniometer stopped moving sometime between 5am and 3pm. The problem was only noticed at 3pm [https://logbooks.jlab.org/entry/3775465]. As a result, a few runs have unknown diamond orientation [https://logbooks.jlab.org/entry/3775587],[https://logbooks.jlab.org/entry/3775590]
 
#** Repair work on goniometer from 4pm till 7:30pm (no beam) [https://logbooks.jlab.org/entry/3775592]
 
#** Repair work on goniometer from 4pm till 7:30pm (no beam) [https://logbooks.jlab.org/entry/3775592]
#** At 10pm, lost HV on TAGH 121-127 and beam halo. HV crate T8-1-BOT has died and wouldn't boot. Repair postponed until next morning [https://logbooks.jlab.org/entry/3775740], [https://logbooks.jlab.org/entry/3775804]
+
#** At 10pm, lost HV on TAGH 121-127 and beam halo. HV crate T8-1-BOT has died and wouldn't boot. Repairs were postponed until next morning [https://logbooks.jlab.org/entry/3775740], [https://logbooks.jlab.org/entry/3775804]
 
#* Sunday:
 
#* Sunday:
#** Night shift takes data with TAGH hole [https://logbooks.jlab.org/files/2020/02/3775916/rs_page10.png]
+
#** Night shift took data with TAGH hole [https://logbooks.jlab.org/files/2020/02/3775916/rs_page10.png]
 
#** No beam 8:15am-9:15pm (ARC8 magnet overheating)
 
#** No beam 8:15am-9:15pm (ARC8 magnet overheating)
 
#** 9:30am-10:30am Controlled tagger access by Nick to repair T8-1-BOT [https://logbooks.jlab.org/entry/3776037]
 
#** 9:30am-10:30am Controlled tagger access by Nick to repair T8-1-BOT [https://logbooks.jlab.org/entry/3776037]
#** Beni conducts ST counter SiPMT tests [https://logbooks.jlab.org/entry/3776046]
+
#** Beni conducted ST counter SiPMT tests [https://logbooks.jlab.org/entry/3776046] and raised TOF HV.
#** Finally, beam is back at 9:15pm.
+
#** Finally, beam came back at 9:15pm.
 
#* Production
 
#* Production
 
#** In all the chaos over weekend, we managed to collect 7.9B triggers. However, 1.9B events have an unknown diamond orientation, and 1.7B tirggers have beam energy hole.
 
#** In all the chaos over weekend, we managed to collect 7.9B triggers. However, 1.9B events have an unknown diamond orientation, and 1.7B tirggers have beam energy hole.

Latest revision as of 09:39, 5 February 2020

Trigger Spreadsheet

Trigger Counter

Wednesday, February 5

  1. Last 24 hours
    • After RF separator and network issues yesterday morning, a good beam returned at 9:30am.
    • No beam 2:30pm-6:30pm (two vacuum pump failures) [1], [2], [3], [4], [5]
    • HOSS restarted at 6am [6]
    • Production: 3.0B triggers.
  2. Issues
    • The last spare turbo pump [7]
    • Easy recovery for the frozen gluon05 didn't work and led to hard reboot. [8]
    • Noisy hodoscope channel [9]
    • HV on FDC:hv:3:c4:4p had to be lowered.
    • BTA from 4pm to 6:30pm: is it BANU or BNA? [10]
  3. Reports
  4. Plans for today
    • Maintenance day until ~2pm, including 2hrs of NL access - a good opportunity for opportunistic access.
    • Harp scan
    • Production

Tuesday, February 4

  1. Last 24 hours
    • No beam: 11pm - 2:30am (beam tunning)
    • Bad beam: since 5am - unstable and shifted by 3mm at AC (5th path separator issues).
    • 9:30am: The latest harp scan [11]
    • About 3.2B production triggers.
  2. Changes
    • 2pm: Same AMO reference in RootSpy as in cohbream gui [12]
    • 4pm: A change in the data-taking procedure [13]:
      • MCC should insert a dumplette before each no-beam goniometer movement
      • Two production runs in a row for each radiator configuration.
  3. Issues
    • Display dumplette location on goniometer GUI
    • Problems with coherent peak at the start of the swing shift. [14],[15]
    • At 8pm, a number of IOC and DAQ stopped working for about 10 minutes. A network glitch is suspected. [16]
    • Issue with EPICS archiving [17]
  4. Reports
    • Ratio of rates from HOSS [18]
    • More on ratio of rates [19]
    • Drifting beam energy [20]
  5. Plans for today
    • Production, production and more production.

Monday, February 3

  1. Last 72 hours
    • Friday:
      • No beam 10am-12pm (BLA calibration). Opportunistic Hall access.
      • No beam 3pm-4pm (MCC software update).
      • No beam 4pm-11pm (lost vacuum in Hall C transport [21]).
    • Saturday:
      • Goniometer stopped moving sometime between 5am and 3pm. The problem was only noticed at 3pm [22]. As a result, a few runs have unknown diamond orientation [23],[24]
      • Repair work on goniometer from 4pm till 7:30pm (no beam) [25]
      • At 10pm, lost HV on TAGH 121-127 and beam halo. HV crate T8-1-BOT has died and wouldn't boot. Repairs were postponed until next morning [26], [27]
    • Sunday:
      • Night shift took data with TAGH hole [28]
      • No beam 8:15am-9:15pm (ARC8 magnet overheating)
      • 9:30am-10:30am Controlled tagger access by Nick to repair T8-1-BOT [29]
      • Beni conducted ST counter SiPMT tests [30] and raised TOF HV.
      • Finally, beam came back at 9:15pm.
    • Production
      • In all the chaos over weekend, we managed to collect 7.9B triggers. However, 1.9B events have an unknown diamond orientation, and 1.7B tirggers have beam energy hole.
  2. Changes
    • Change in TPOL readout [31], [32]
    • New DIRC SiPM TDC reference timing [33] - apparently, it's still not in ccdb.
    • New TOF high voltages [34]
  3. Issues
    • TAGM is "immobilized" to keep goniometer moving.
    • TPOL slot 13 channel 3 is always saturated [35]
    • Remote reset cable for T8-1-BOT needs to be repaired.[36]
    • FDC HV channel 2:c4:4p was in constant trip loop and was set to lower HV [37], [38]
    • TOF T:45 20V difference between HV setpoint and readback.
    • Gluon05 needs to be rebooted almost daily.
    • As ususal, new DIRC holes require DAQ reboots.
    • Do we need a dumplette inserted for all goniometer movements? [39]
  4. Noteworthy
    • MCC sees our radiator IN & OUT at the same time [40]
  5. Reports
    • Ratio of rates [41]
    • Vertex plots for empty target [42]
  6. Plans for today
    • Harp scan
    • Production

Friday, January 31

  1. Last 24 hours
    • JD70-106 47um diamond alignment till 4pm [43], [44]
    • Ion chambers had to be masked for alignment [45], [46]
    • Production since 4pm (~3.5B triggers)
  2. Issues
    • JD70-105 keeps degrading [47]
    • Periodic holes in DIRC occupancy [48]. Any way to recover without full DAQ reboot?
    • "Disappeared" DIRC SiPM TDC [49] - its timing recalibration is not done yet
    • Oh yes, Great Battle of the Mouse for 3 hrs :) [50]
  3. Reports
    • More on initial PS enhancement [51]
  4. Plans for today
    • We may (or may not) have ~30min for access at 10am
    • Production

Thursday, January 30

  1. Last 24 hours
    • Harp scan (~9am) [52]
    • Alignment of JD70-106 47um diamond (9:30am till 6pm) [53]
    • Production at 350nA (since 6pm). About 2.6B triggers collected.
  2. Issues
    • DIRC N-board lost connectivity for 30 minutes [54]
    • Gamma radiation at the racks [55]
    • Uncoupling of DIRC and FCAL light censors [56],[57]
    • Online monitoring issues [58] and fixed calibrations [59], [60]
  3. Reports
    • Initial PS enhancement Spring 2020 [61]
  4. Plans for today
    • Any more work on diamond alignment?
    • Production