Difference between revisions of "Run Planning Meeting Notes, Jan 30-Feb 05, 2020"
From GlueXWiki
m |
m |
||
Line 18: | Line 18: | ||
# Last 72 hours | # Last 72 hours | ||
#* No beam since 4pm Friday due to lost vacuum in Hall C transport [https://logbooks.jlab.org/entry/3774952] | #* No beam since 4pm Friday due to lost vacuum in Hall C transport [https://logbooks.jlab.org/entry/3774952] | ||
+ | # Changes | ||
+ | #* Change in TPOL readout [https://logbooks.jlab.org/entry/3774906] | ||
+ | #* New DIRC SiPM TDC reference timing [https://logbooks.jlab.org/entry/3774941] | ||
# Issues | # Issues | ||
#* MCC sees our radiator IN & OUT at the same time [https://logbooks.jlab.org/entry/3774793] | #* MCC sees our radiator IN & OUT at the same time [https://logbooks.jlab.org/entry/3774793] | ||
# Reports | # Reports | ||
+ | #* Ratio of rates [https://logbooks.jlab.org/entry/3774762] | ||
+ | #* Vertex plots for empty target [https://logbooks.jlab.org/entry/3774857] | ||
# Plans for today | # Plans for today | ||
Revision as of 18:55, 31 January 2020
Contents
Wednesday, February 5
- Last 24 hours
- Issues
- Reports
- Plans for today
Tuesday, February 4
- Last 24 hours
- Issues
- Reports
- Plans for today
Monday, February 3
- Last 72 hours
- No beam since 4pm Friday due to lost vacuum in Hall C transport [1]
- Changes
- Issues
- MCC sees our radiator IN & OUT at the same time [4]
- Reports
- Plans for today
Friday, January 31
- Last 24 hours
- Issues
- Reports
- More on initial PS enhancement [15]
- Plans for today
- We may (or may not) have ~30min for access at 10am
- Production
Thursday, January 30
- Last 24 hours
- Issues
- Reports
- Initial PS enhancement Spring 2020 [25]
- Plans for today
- Any more work on diamond alignment?
- Production