= Wednesday January 24 =
 +
=== Past 24 hours ===
 +
* Beam study, with Hall D access. Then, production on diamond. ABU= 12.2 h for the day.
 +
 +
=== Shift Reports ===
 +
* [https://logbooks.jlab.org/entry/4116249 Day shift summary]
 +
* [https://logbooks.jlab.org/entry/4116506 Swing shift summary]
 +
* [https://logbooks.jlab.org/entry/4116677 Owl shift summary]
 +
* [https://logbooks.jlab.org/entry/4116888 Early Riser shift summary]
 +
 +
=== Reports ===
 +
* During Access, a certain number of problems were fixed:
 +
** [https://logbooks.jlab.org/entry/4116277 The TAGH HV crate power was cycled (A. Somov)] (See original problem [https://logbooks.jlab.org/entry/4116043 here])
 +
** [https://logbooks.jlab.org/entry/4116279 Target remote control was fixed (C. Carlin)]
 +
** [https://logbooks.jlab.org/entry/4116374 Misbehaving pressure sensor was taken care of(Scot)]. [It looks fine now (Beni)] and [agrees with Newportnews weather station (Naomi)]. Spare sensor was ordered. Should we restore the sensor in the alarm and the usual instruction to stop run if the alarm goes off?
 +
** NMR probe fixed (Tim/Scot). Then [https://logbooks.jlab.org/entry/4116505 it froze again] until this morning, 6:24am. [https://logbooks.jlab.org/entry/4116955 Now it is working again after Scot cycled it]. Linked to Tagger magnet DCCT current sensor cycling. 
 +
** Malte and Mark Dalton worked on FCal.
 +
** Justin worked on DIRC LED issue.
 +
** Scot had Vlad's chiller taken out of the Hall.
 +
* [https://logbooks.jlab.org/entry/4116246 Diamond orientations are consistent with 2020 (Alexander Austregesilo)]
 +
* [https://logbooks.jlab.org/entry/4117016 Energy monitoring for Winter 2023 GlueX-II run]
 +
 +
=== Issues ===
 +
* [https://logbooks.jlab.org/entry/4116334 Start counter 96 degree rotation in cabling or software space (Simon)]
 +
* [https://logbooks.jlab.org/entry/4116427 DIRC LED TDC missing (David Lawrence, Justin]
 +
* [https://logbooks.jlab.org/entry/4116199 TOF timing (Beni)]. Later [https://logbooks.jlab.org/entry/4116298 fixed by Sean].
 +
* [https://logbooks.jlab.org/entry/4116959 Long DAQ problem:~1.5h (Alison Laduke/Sergei Furletov)]. See also [https://logbooks.jlab.org/entry/4116888 Early Riser shift summary]
 +
* BCM calibration. Accelerator instrumentation group informed us that last BLA calibration was done in 2021 (beside that done last Thursday, 01/19/2023? To be confirmed) and recommend Ops to do one at each start of the run period.
 +
* [https://logbooks.jlab.org/entry/4116888 A request for the kitchen lights to be fixed should be submitted next time there is beam downtime.]
 +
 +
=== Plans ===
 +
* Production (300 nA, 2h runs) with cycle:
 +
**2 runs para(0/90)
 +
**2 runs perp(0/90)
 +
**2 runs para(45/135)
 +
**2 runs perp(45/135)
 +
**1 run amo (use it to rejuvenate amo reference in CBREM GUI)
 +
* Trigger fine tuning Thursday? (A. Somov)
 +
 +
= Tuesday January 24 =
 +
=== Past 24 hours ===
 +
* Production on diamond. Trippy beam, but good availability. ABU=16.2h for the day
 +
 +
=== Shift Reports ===
 +
* [https://logbooks.jlab.org/entry/4115595 Day shift summary]
 +
* [https://logbooks.jlab.org/entry/4115786 Swing shift summary]
 +
* [https://logbooks.jlab.org/entry/4116022 Owl shift summary]
 +
* [https://logbooks.jlab.org/entry/4116083 Early Riser shift summary]
 +
 +
=== Reports ===
 +
* [https://logbooks.jlab.org/files/2023/01/4115541/Hall%20D%20Electron%20Beam%20Harp%20Scan%202D%20Fitting%20Tool.pdf Beam profile from Harp scan done Monday morning looks good]
 +
* [https://logbooks.jlab.org/entry/4115569 Coherent peak enhancement fit for 2023 (Justin)]
 +
* [https://logbooks.jlab.org/entry/4115527 Start Counter performance (Beni)]
 +
* [https://logbooks.jlab.org/entry/4115731 Rates comparison for GlueX, PrimEx and CPP/NPP (Alexandre D.)]
 +
* [https://logbooks.jlab.org/entry/4115667 Start Counter detector walk (Beni)]
 +
 +
=== Issues ===
 +
* [https://logbooks.jlab.org/entry/4116043 Tagger Hodoscope HV communication problem (Jon Zarling)]
 +
* Main trigger scaler freeze goes unnoticed: [https://logbooks.jlab.org/entry/4114856 Sunday], [https://logbooks.jlab.org/entry/4116137 Monday] Can we include them in the scaler summary gui, so it is easy for the shift people to see them?
 +
* [https://logbooks.jlab.org/entry/4115830 NMR probe not communicating.]. It started around 4pm Monday. DCCT current monitor for the tagger is also down.([https://logbooks.jlab.org/entry/4116083 See also Early Riser shift summary])
 +
 +
=== Plans ===
 +
* 4h of beam studies + 2h beam restoration). Tagger and Hall to be surveyed around 9pm:
 +
** Safety Walkthrough (M. Dalton + trainee(s))?
 +
** Scot to access to take out Vlad's chiller
 +
** Tagger access for HV communication issue?
 +
** Investigate the faulty pressure sensor?
 +
** Chris Carlin to fix the target controls
 +
* Production (300 nA, 2h runs) with cycle:
 +
**2 runs para(0/90)
 +
**2 runs perp(0/90)
 +
**2 runs para(45/135)
 +
**2 runs perp(45/135)
 +
**1 run amo
 +
 
= Monday January 23 =
 
= Monday January 23 =
 
=== Past 72 hours ===
 
=== Past 72 hours ===
 
* Beam was off from Friday 7:30am to Saturday 2am due to vacuum issue in south linac. Friday ABU: 4.0h
 
* Beam was off from Friday 7:30am to Saturday 2am due to vacuum issue in south linac. Friday ABU: 4.0h
 
* Saturday: Ran on amorphous (goni), 300 nA. Until Sunday 9am when Hovanes started diamond alignment. Saturday ABU: 18.6h
 
* Saturday: Ran on amorphous (goni), 300 nA. Until Sunday 9am when Hovanes started diamond alignment. Saturday ABU: 18.6h
* Sunday 9am-**: diamond alignment. Sunday ABU:  
+
* Sunday 9am-5:30pm: diamond alignment. '''Sunday 8:30pm - Monday 7:30am: First production 0/90/45/135/amo cycle''' (see [https://logbooks.jlab.org/entry/4115218 CBrem peak]). Then did Harp scans. Sunday ABU: 14.3h
  
 
=== Shift Reports ===
 
=== Shift Reports ===
* Day shift summary [https://logbooks.jlab.org/entry/4113703 Friday], [https://logbooks.jlab.org/entry/4114358 Saturday], [Sunday]
+
* Day shift summary [https://logbooks.jlab.org/entry/4113703 Friday], [https://logbooks.jlab.org/entry/4114358 Saturday], [https://logbooks.jlab.org/entry/4114927 Sunday]
* Swing shift summary [https://logbooks.jlab.org/entry/4113892 Friday], [https://logbooks.jlab.org/entry/4114507 Saturday], [Sunday]
+
* Swing shift summary [https://logbooks.jlab.org/entry/4113892 Friday], [https://logbooks.jlab.org/entry/4114507 Saturday], [https://logbooks.jlab.org/entry/4115112 Sunday]
* Owl shift summary [https://logbooks.jlab.org/entry/4114007 Saturday], [https://logbooks.jlab.org/entry/4114730 Sunday], [Monday]
+
* Owl shift summary [https://logbooks.jlab.org/entry/4114007 Saturday], [https://logbooks.jlab.org/entry/4114730 Sunday], [https://logbooks.jlab.org/entry/4115243 Monday]
* Early Riser shift summary [https://logbooks.jlab.org/entry/4114137 Saturday], [https://logbooks.jlab.org/entry/4114774 Sunday], [Monday]
+
* Early Riser shift summary [https://logbooks.jlab.org/entry/4114137 Saturday], [https://logbooks.jlab.org/entry/4114774 Sunday], [https://logbooks.jlab.org/entry/4115380 Monday]
  
 
=== Reports ===
 
=== Reports ===
 +
* [https://logbooks.jlab.org/entry/4114903 Diamond alignment (Hovanes)]. See also [https://logbooks.jlab.org/entry/4114981 here] and [https://logbooks.jlab.org/entry/4114995 here] and [https://logbooks.jlab.org/entry/4115071 here]
 
* [https://logbooks.jlab.org/entry/4113672 Empty target vertex reconstruction (Simon Taylor)]
 
* [https://logbooks.jlab.org/entry/4113672 Empty target vertex reconstruction (Simon Taylor)]
* [https://logbooks.jlab.org/entry/4113681 TAGM check) and also [https://logbooks.jlab.org/entry/4114603 here] (Richard Jones)
+
* [https://logbooks.jlab.org/entry/4113681 TAGM check] and also [https://logbooks.jlab.org/entry/4114603 here] (Richard Jones)
 
+
 
* [https://logbooks.jlab.org/entry/4113756 DIRC LED performance (Bill)]
 
* [https://logbooks.jlab.org/entry/4113756 DIRC LED performance (Bill)]
 
* [https://logbooks.jlab.org/entry/4114222 FCAL occupancy plots (Churaman)]
 
* [https://logbooks.jlab.org/entry/4114222 FCAL occupancy plots (Churaman)]
Line 20: Line 95:
 
* [https://logbooks.jlab.org/entry/4114336 cdc currents (Beni)]
 
* [https://logbooks.jlab.org/entry/4114336 cdc currents (Beni)]
 
* [https://logbooks.jlab.org/entry/4114884 TOF timing resolution  (Beni)]
 
* [https://logbooks.jlab.org/entry/4114884 TOF timing resolution  (Beni)]
 
+
* [https://logbooks.jlab.org/entry/4115456 tagger field after power glicth (Alexandre Deur)]
  
 
=== Issues ===
 
=== Issues ===
* RC volunteers needed (Beni's RC week because of his surgery, and Susan's week because she had to cancel her trip to the US). Hovanes and Simon volunteered to cover the two weeks.
+
* 2 RC volunteers were needed (one for Beni's RC week because of his surgery, and another for Susan S's week because she had to cancel her trip to the US). Hovanes and Simon volunteered to cover the two weeks.
 
* Numerous pressure alarms. [https://logbooks.jlab.org/entry/4114307 Sensor problem? Since Saturday morning, instruction from Lubomir are that we should only acknowledge the alarms. No need for stoping the ongoing run.] [https://logbooks.jlab.org/entry/4114263 See also here.] [https://logbooks.jlab.org/entry/4114344 The suspicious sensor has been removed from the alarm (Hovanes)]
 
* Numerous pressure alarms. [https://logbooks.jlab.org/entry/4114307 Sensor problem? Since Saturday morning, instruction from Lubomir are that we should only acknowledge the alarms. No need for stoping the ongoing run.] [https://logbooks.jlab.org/entry/4114263 See also here.] [https://logbooks.jlab.org/entry/4114344 The suspicious sensor has been removed from the alarm (Hovanes)]
 
* Beam energy oscillation investigation: Several accelerator experts are looking at it. No consensus whether it is real or not. Since it is at the MeV level, it should not be an issue for GlueX (but it is for accelerator).  
 
* Beam energy oscillation investigation: Several accelerator experts are looking at it. No consensus whether it is real or not. Since it is at the MeV level, it should not be an issue for GlueX (but it is for accelerator).  
Line 32: Line 107:
 
**[https://logbooks.jlab.org/entry/4113961 Target communication lost around 1pm Friday]. [https://logbooks.jlab.org/entry/4113908 Alarm acknowledged by shift crew without action or calling expert. New shift noticed this and called Hovanes.] Hovanes informed Alexandre who checked what was the issue and call then Chris Carlin. Chris C. could not come (catching a flight at the airport) but instructed the crew to switch the the back-up IOC, which apparently fixed the issue. However, the controlled came back in a confused state (Full but with heater on, an incompatible situation) so Alexandre informed Chris Keith [https://logbooks.jlab.org/entry/4113972 who went in (beam was off for repair during the whole event) with the shift leader (Dene) and partly fixed the issue by switching the target to local control.]
 
**[https://logbooks.jlab.org/entry/4113961 Target communication lost around 1pm Friday]. [https://logbooks.jlab.org/entry/4113908 Alarm acknowledged by shift crew without action or calling expert. New shift noticed this and called Hovanes.] Hovanes informed Alexandre who checked what was the issue and call then Chris Carlin. Chris C. could not come (catching a flight at the airport) but instructed the crew to switch the the back-up IOC, which apparently fixed the issue. However, the controlled came back in a confused state (Full but with heater on, an incompatible situation) so Alexandre informed Chris Keith [https://logbooks.jlab.org/entry/4113972 who went in (beam was off for repair during the whole event) with the shift leader (Dene) and partly fixed the issue by switching the target to local control.]
 
**We can monitor the target, but not control it remotely (switch empty <=> full). For the moment, this is not a crucial problem.
 
**We can monitor the target, but not control it remotely (switch empty <=> full). For the moment, this is not a crucial problem.
* Numerous DIRC alarms Saturday, see [https://logbooks.jlab.org/entry/4114519 this entry], [https://logbooks.jlab.org/entry/4114518 this one], and the comments in the [https://logbooks.jlab.org/entry/4114358 day] and [https://logbooks.jlab.org/entry/4114507 swing] shift summaries.  
+
* Numerous DIRC alarms Saturday, see [https://logbooks.jlab.org/entry/4114519 this entry], [https://logbooks.jlab.org/entry/4114518 this one], and the comments in the [https://logbooks.jlab.org/entry/4114358 day] and [https://logbooks.jlab.org/entry/4114507 swing] shift summaries.
  
 
=== Plans ===
 
=== Plans ===
 
* Production on amorphous (Goni, 300 nA) until the diamond is aligned.
 
* Production on amorphous (Goni, 300 nA) until the diamond is aligned.
 
* Diamond alignment: Sunday morning, ~9am. (Hovanes)
 
* Diamond alignment: Sunday morning, ~9am. (Hovanes)
* Then production on diamond radiator, 4 orientations + amo. 300 nA.
+
* Then production on diamond radiator, 4 orientations + amo. 300 nA. Presently, we do each orientation once (not twice) and each run is nominally 2h, including the amo run.
 +
* Tomorrow (Tuesday, 24th: 4h of beam studies + 2h beam restoration):
 +
** ?Safety Walkthrough (M. Dalton + trainee(s))?
 +
** Scot to access to take out Vlad's chiller
 +
** ?Investigate the faulty pressure sensor?
 +
** ?Chris Carlin to fix the target controls?
 
* [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Spring2023#Runplan Link to runplan]
 
* [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Spring2023#Runplan Link to runplan]
  

Latest revision as of 09:06, 25 January 2023

Wednesday January 24

Past 24 hours

  • Beam study, with Hall D access. Then, production on diamond. ABU= 12.2 h for the day.

Shift Reports

Reports

Issues

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo (use it to rejuvenate amo reference in CBREM GUI)
  • Trigger fine tuning Thursday? (A. Somov)

Tuesday January 24

Past 24 hours

  • Production on diamond. Trippy beam, but good availability. ABU=16.2h for the day

Shift Reports

Reports

Issues

Plans

  • 4h of beam studies + 2h beam restoration). Tagger and Hall to be surveyed around 9pm:
    • Safety Walkthrough (M. Dalton + trainee(s))?
    • Scot to access to take out Vlad's chiller
    • Tagger access for HV communication issue?
    • Investigate the faulty pressure sensor?
    • Chris Carlin to fix the target controls
  • Production (300 nA, 2h runs) with cycle:
    • 2 runs para(0/90)
    • 2 runs perp(0/90)
    • 2 runs para(45/135)
    • 2 runs perp(45/135)
    • 1 run amo

Monday January 23

Past 72 hours

  • Beam was off from Friday 7:30am to Saturday 2am due to vacuum issue in south linac. Friday ABU: 4.0h
  • Saturday: Ran on amorphous (goni), 300 nA. Until Sunday 9am when Hovanes started diamond alignment. Saturday ABU: 18.6h
  • Sunday 9am-5:30pm: diamond alignment. Sunday 8:30pm - Monday 7:30am: First production 0/90/45/135/amo cycle (see CBrem peak). Then did Harp scans. Sunday ABU: 14.3h

Shift Reports

Reports

Issues

Plans

  • Production on amorphous (Goni, 300 nA) until the diamond is aligned.
  • Diamond alignment: Sunday morning, ~9am. (Hovanes)
  • Then production on diamond radiator, 4 orientations + amo. 300 nA. Presently, we do each orientation once (not twice) and each run is nominally 2h, including the amo run.
  • Tomorrow (Tuesday, 24th: 4h of beam studies + 2h beam restoration):
    •  ?Safety Walkthrough (M. Dalton + trainee(s))?
    • Scot to access to take out Vlad's chiller
    •  ?Investigate the faulty pressure sensor?
    •  ?Chris Carlin to fix the target controls?
  • Link to runplan

Friday January 20

Past 24 hours

Shift Reports

Reports

Issues

Plans

  • Thursday evening and Friday night:
    • Once beam come back, do Harp scans.
    • FCup test of our beam dump BCM.
    • Run 1h on the amo radiator of the goni (baseline for next runs below). 250 nA
    • Run 2h on 0.19E-4 RL amo radiator on radiator ladder (250 nA).
    • Run 2h on 1.12E-4 RL amo radiator on radiator ladder (250 nA).
    • Run (until the beam is taken away in the morning) on 3.4E-4 RL amo radiator on radiator ladder (250 nA).
  • Beam off starting Friday morning around 7:30am to fix vacuum issue in south linac, until 4pm(?).
  • When the beam comes back:
    • Harp scans
    • Production on goni amo radiator at 300 nA until Sunday morning.
  • Hall access:
    • Sergey F.
  • Diamond alignment: Sunday morning, ~9am.
  • Until then production on amorphous.
  • Link to runplan

Thursday January 19

Past 24 hours

  • Ran on empty target until 7:20am. Then, beam was taken away for beam and RF study and acceptable beam came back only Thursday at 1:10am. ABU= 4h for the day
  • refilled the target around 4:15pm.
  • Several accesses done during the day:
    • Scot
    • Sergey
    • David Lawrence
    • Cody
  • Took amorphous data, starting around 1:10am after aborted attempt to check diamond alignment.

Shift Reports

Reports

Issues

Plans

  • Beam off starting around 10am for RF study, nominally until 4pm+/-4h.
  • Hall in controlled access?
  • Diamond alignment: Friday day ? (Hovanes unavailable today)
  • Until Friday day, production on amorphous?
  • Link to runplan