Run Planning Meeting Notes, July 07 - July 14, 2022

From GlueXWiki
Revision as of 22:04, 6 July 2022 by Ilarin (Talk | contribs) (Reports)

Jump to: navigation, search
Back to Run Coordination Meetings:Summer2022

Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Wednesday July 7

Past 24 hours

  • Malte and Mark worked on FCAL modules replacement [1]
  • One of the RF crates had been disconnected, Beni fixed it [2]
  • Bobby and others worked in the tagger hall during the day. At 3:30pm Bobby noticed that the IOC for the NMR was not responding properly. MCC rebooted the IOC crate. Afterwards, it was still locked on zero and there was still a Comm Status error [3]
  • Beni found that the solenoid controls hung, and restarted the ramping, which was helpful.
  • Had minor issues with DAQ at 7.00pm: ROCFDC11 error: timeout error on FA125, every 3 seconds. (fADC125 in fdc11 slot 3 was replaced during day time [4]) Sergei worked out the DAQ issue at 7.50pm
  • Established operating field of solenoid at 8:30pm.
  • production data taking continued on Pb

Shift reports

Reports

  • Coherent peak position drifts on 4th of July

Issues

  • Hovanes pointed out that something strange happened during solenoid ramping up [5]

Plans

  • maintenance day: beam will go away 7:30am, 8 hours maintenance, followed by beam restoration and high current beam tuning for HallC
    • please access hall after 9am: other halls have priority
    • ramp solenoid to 800A for cyro comprssor swtch
    • FCAL base replacement
    • Tagger NMR inspection
    • Fix TOF RF signal