Difference between revisions of "Run Planning Meeting Notes, July 27-August 5, 2020"
From GlueXWiki
(→July 27th-Aug. 3rd) |
(→July 27th-Aug. 3rd) |
||
Line 8: | Line 8: | ||
*Shift Started on Aug. 1st, 8am. | *Shift Started on Aug. 1st, 8am. | ||
− | August 1st-2nd : investigating and attempting to fix [https://logbooks.jlab.org/entry/3819118 a problem with the front-end of the TagM]. Did two long accesses to tagger, but the [https://logbooks.jlab.org/entry/3819589 problem remains]. | + | August 1st-2nd : investigating and attempting to fix [https://logbooks.jlab.org/entry/3819118 a problem with the front-end of the TagM]. Did two long accesses to tagger, but the [https://logbooks.jlab.org/entry/3819589 problem remains]. Due to this, [https://logbooks.jlab.org/entry/3819665 the runplan for August 3-4 has been reorganized] |
*CW beam arrived around 3am on Aug. 2nd, followed by beam quality checks. | *CW beam arrived around 3am on Aug. 2nd, followed by beam quality checks. | ||
Line 15: | Line 15: | ||
**[https://logbooks.jlab.org/entry/3819406 Beam position optimized (?)], however transmission [https://logbooks.jlab.org/entry/3819632 doesn't appear to be optimal] | **[https://logbooks.jlab.org/entry/3819406 Beam position optimized (?)], however transmission [https://logbooks.jlab.org/entry/3819632 doesn't appear to be optimal] | ||
**[https://logbooks.jlab.org/entry/3819651 trigger checked out] | **[https://logbooks.jlab.org/entry/3819651 trigger checked out] | ||
+ | **Radiation level study done. | ||
+ | **CDC HV scan ongoing. | ||
+ | |||
+ | Issues: | ||
+ | *TagM | ||
+ | *We often get [https://logbooks.jlab.org/entry/3819644 less beam current than requested] | ||
+ | *[https://logbooks.jlab.org/entry/3819644 DAQ start run issue] | ||
+ | *[https://logbooks.jlab.org/entry/3819644 Difficulty in setting CDC HV for CDV HV scan], see also [https://logbooks.jlab.org/entry/3819845 Keigo's entry] | ||
Upcoming days: | Upcoming days: |
Revision as of 06:57, 3 August 2020
<- Back to Run coordination meeting page
July 27th-Aug. 3rd
- Beni ramped up the solenoid on Aug. 1st. However, due to a problem with the PXI readout, it was ramped down. The solenoid was ramp-up again (Aug. 2nd) to its nominal 1350A, this time without problem.
- Target was cooled (C. Keith) and latter filled without problem (Aug. 1st)
- Shift Started on Aug. 1st, 8am.
August 1st-2nd : investigating and attempting to fix a problem with the front-end of the TagM. Did two long accesses to tagger, but the problem remains. Due to this, the runplan for August 3-4 has been reorganized
- CW beam arrived around 3am on Aug. 2nd, followed by beam quality checks.
- Radiation levels are good.
- Beam convergence is good
- Beam position optimized (?), however transmission doesn't appear to be optimal
- trigger checked out
- Radiation level study done.
- CDC HV scan ongoing.
Issues:
- TagM
- We often get less beam current than requested
- DAQ start run issue
- Difficulty in setting CDC HV for CDV HV scan, see also Keigo's entry
Upcoming days:
- TagM communication issue
- Week 1 time chart
- Richard plan for Act. Col. test