Difference between revisions of "Run Planning Meeting Notes, July 27-August 5, 2020"

From GlueXWiki
Jump to: navigation, search
m (Aug. 3rd)
Line 66: Line 66:
 
*[https://logbooks.jlab.org/entry/3819445 Richard plan for Act. Col. test ]
 
*[https://logbooks.jlab.org/entry/3819445 Richard plan for Act. Col. test ]
 
*Thursday: 1->5 pass change for Hall B. Hall A on-line.
 
*Thursday: 1->5 pass change for Hall B. Hall A on-line.
 +
*Tuesday 11th: Maintenance day?
 +
 +
 +
== Aug. 4th  ==
 +
 +
[https://logbooks.jlab.org/entry/3819971 Run plan for today]
 +
 +
Tasks completed:
 +
*None: recovering from Isaias hurricane, with CEBAF going down on 08/03, ~2:30am
 +
 +
Tasks to be done:
 +
*Hovanes to check JD70-105 diamond alignement
 +
*Sacha finalized the trigger check out
 +
*One production cycle at 150nA
 +
*Start regular production.
 +
 +
Issues:
 +
*[https://logbooks.jlab.org/entry/3820217 Instable beam current] (since the start of the run)
 +
 +
Reports:
 +
*[https://logbooks.jlab.org/entry/3820433 leakage current test of active collimator]
 +
Upcoming days:
 +
*[https://halldweb.jlab.org/wiki/images/6/68/Week1.png Week 1 time chart]
 +
*[https://logbooks.jlab.org/entry/3819445 Richard plan for Act. Col. test ]
 +
*Thursday?/Friday?: 1->5 pass change for Hall B. Hall A on-line.
 
*Tuesday 11th: Maintenance day?
 
*Tuesday 11th: Maintenance day?

Revision as of 22:58, 4 August 2020

<- Back to Run coordination meeting page


July 27th-Aug. 2nd

  • Beni ramped up the solenoid on Aug. 1st. However, due to a problem with the PXI readout, it was ramped down. The solenoid was ramp-up again (Aug. 2nd) to its nominal 1350A, this time without problem.
  • Target was cooled (C. Keith) and latter filled without problem (Aug. 1st)
  • Shift Started on Aug. 1st, 8am.

August 1st-2nd : investigating and attempting to fix a problem with the front-end of the TagM. Did two long accesses to tagger, but the problem remains. Due to this, the runplan for August 3-4 has been reorganized

Issues:

Upcoming days:

Aug. 3rd

Run plan for today

Tasks completed:

Tasks to be done:

  • Hovanes to check JD70-105 diamond alignement
  • Sacha finalized the trigger check out
  • One production cycle at 150nA
  • Start regular production.

Issues:

Reports:

Upcoming days:


Aug. 4th

Run plan for today

Tasks completed:

  • None: recovering from Isaias hurricane, with CEBAF going down on 08/03, ~2:30am

Tasks to be done:

  • Hovanes to check JD70-105 diamond alignement
  • Sacha finalized the trigger check out
  • One production cycle at 150nA
  • Start regular production.

Issues:

Reports:

Upcoming days: