Run Planning Meeting Notes, July 27-August 5, 2020

From GlueXWiki
Revision as of 08:23, 5 August 2020 by Deurpam (Talk | contribs) (Aug. 4th)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

<- Back to Run coordination meeting page


July 27th-Aug. 2nd

  • Beni ramped up the solenoid on Aug. 1st. However, due to a problem with the PXI readout, it was ramped down. The solenoid was ramp-up again (Aug. 2nd) to its nominal 1350A, this time without problem.
  • Target was cooled (C. Keith) and latter filled without problem (Aug. 1st)
  • Shift Started on Aug. 1st, 8am.

August 1st-2nd : investigating and attempting to fix a problem with the front-end of the TagM. Did two long accesses to tagger, but the problem remains. Due to this, the runplan for August 3-4 has been reorganized

Issues:

Upcoming days:

Aug. 3rd

Run plan for today

Tasks completed:

Tasks to be done:

  • Hovanes to check JD70-105 diamond alignement
  • Sacha finalized the trigger check out
  • One production cycle at 150nA
  • Start regular production.

Issues:

Reports:

Upcoming days:


Aug. 4th

Tasks completed:

  • None: recovering from Isaias hurricane, with CEBAF going down on 08/03, ~2:30am

Tasks to be done:

  • Hovanes to check JD70-105 diamond alignement
  • Sacha finalized the trigger check out
  • One production cycle at 150nA
  • Start regular production.

Issues:

Reports:


Run plan for today


Upcoming days: