Difference between revisions of "Run Planning Meeting Notes, June 23 - June 29, 2022"

From GlueXWiki
Jump to: navigation, search
(Thursday June 23)
(Thursday June 23)
Line 12: Line 12:
  
 
#Last 24h:
 
#Last 24h:
#*[https://logbooks.jlab.org/entry/4005879 Inadvertent change to tagger magnet settings] [https://logbooks.jlab.org/entry/4005898 backed out]  
+
#* [https://logbooks.jlab.org/entry/4005879 Inadvertent change to tagger magnet settings] [https://logbooks.jlab.org/entry/4005898 backed out]  
#*[https://logbooks.jlab.org/entry/4005934 Target moved out]
+
#* [https://logbooks.jlab.org/entry/4005934 Target moved out]
#*[https://logbooks.jlab.org/entry/4005968 Richard took the microscope scan data]
+
#* [https://logbooks.jlab.org/entry/4005968 Richard took the microscope scan data]
#*[https://logbooks.jlab.org/entry/4005967 Bleedthrough beam current was very low]  
+
#* [https://logbooks.jlab.org/entry/4005967 Bleedthrough beam current was very low]  
#*Wed evening: The target is out already. Sasha will set up the straight track trigger, then start the TAC run at whatever beam current was chosen earlier.  
+
#* Wed evening: The target is out already. Sasha will set up the straight track trigger, then start the TAC run at whatever beam current was chosen earlier.  
#Shift Summaries [https://logbooks.jlab.org/entry/4005862 day]
+
#Shift Summaries  
 +
#* [https://logbooks.jlab.org/entry/4005862 day]
 
#Reports
 
#Reports
 
#Issues
 
#Issues

Revision as of 16:29, 22 June 2022

↑ Back to Run Coordination Meetings:Summer2022

Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Thursday June 23

  1. Last 24h:
  2. Shift Summaries
  3. Reports
  4. Issues
    • Tagger NMR
    • DIRC sensor
    • DAQ livetime
    • Beam position stability
    • U1-10-TOP MPOD crate
  5. Plans
    • No beam from 6:30am until sometime after 3pm, power shedding.
    • Walk-through at 11am
  6. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.