Difference between revisions of "Run Planning Meeting Notes, Mar 19-Mar 28, 2018"
From GlueXWiki
(Created page with "<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run * [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2018-01/index.html Trigger graphs] * [h...") |
|||
Line 5: | Line 5: | ||
* [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | ||
* [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | ||
+ | |||
+ | == Sunday, March 25 @ 10:00am == | ||
+ | # Accelerator Status | ||
+ | #* No significant progress on increasing total beam power since yesterday | ||
+ | #* Started setting up Hall-B and Hall-D beams on Owl last night | ||
+ | #* Will work on establishing Hall-D and Hall-B beams today | ||
+ | #** RF expert is on site, but may not have anything new to try. May cause some loss in beam stability | ||
+ | #* Likely to go back to working on power issue on Monday when full compliment of experts available. | ||
+ | #** Beam likely to be very unstable for us then. Will know more Monday morning. | ||
+ | #* [https://logbooks.jlab.org/entry/3546359 Beam Authorization] | ||
+ | # Run Plan | ||
+ | #* [[Run_Coordination_Meetings:Fall2017_Spring2018_Run/March_recovery|Restablish Photon beam]] | ||
+ | #* PS High Rate Check | ||
+ | #* CDC Background Studies (Lubomir et al.) | ||
+ | #* Converter thickness study (Alex S.) | ||
+ | #* SSP Study (Alex S.) | ||
+ | #* Production running | ||
+ | #* [https://halldweb.jlab.org/wiki/images/c/c3/Spring18_week11.jpg Time Chart] | ||
+ | # Reports | ||
+ | #* [https://logbooks.jlab.org/entry/3546343 Muon Chamber Noise] | ||
+ | # Safety Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3546144 Rapid Access + Collimator Cave] | ||
== Monday, March 19 @ 8:45am == | == Monday, March 19 @ 8:45am == |
Latest revision as of 09:43, 25 March 2018
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Sunday, March 25 @ 10:00am
- Accelerator Status
- No significant progress on increasing total beam power since yesterday
- Started setting up Hall-B and Hall-D beams on Owl last night
- Will work on establishing Hall-D and Hall-B beams today
- RF expert is on site, but may not have anything new to try. May cause some loss in beam stability
- Likely to go back to working on power issue on Monday when full compliment of experts available.
- Beam likely to be very unstable for us then. Will know more Monday morning.
- Beam Authorization
- Run Plan
- Restablish Photon beam
- PS High Rate Check
- CDC Background Studies (Lubomir et al.)
- Converter thickness study (Alex S.)
- SSP Study (Alex S.)
- Production running
- Time Chart
- Reports
- Safety Issues
Monday, March 19 @ 8:45am
- Notes from the previous 48 hours:
- 8:00am MCC meeting report:
- transformers
- 2nd Transformer installed and powered up Saturday
- Work to restore cryo operation underway
- Halls asked to man counting house 24/7 starting Fri. 3/23
- Beam restoration over weekend with Physics expected to start Wed. 3/28
- transformers
- Solenoid ramped down
- Hall D in restricted access, tagger hall
- 8:00am MCC meeting report:
- Reports:
- AOB