(Thursday, Mar. 21 at 08:45)
Line 13: Line 13:
 
#* Beam recovery delayed due to (1) issue in the injector, resolved by evening, then (2) UPS battery needs replacement in the north linac.  
 
#* Beam recovery delayed due to (1) issue in the injector, resolved by evening, then (2) UPS battery needs replacement in the north linac.  
 
# Issues
 
# Issues
#* low counts seen in bcal sector ([https://logbooks.jlab.org/entry/3670196])
+
#* low counts seen in bcal sector ([https://logbooks.jlab.org/entry/3670196 logbook entry 3670196])
 
# Reports
 
# Reports
 
#* helium target refilled, ready
 
#* helium target refilled, ready

Revision as of 07:37, 21 March 2019

Thursday, Mar. 21 at 08:45

  1. Past 24 hours:
    • RF recovery during the day shift
    • Beam recovery delayed due to (1) issue in the injector, resolved by evening, then (2) UPS battery needs replacement in the north linac.
  2. Issues
  3. Reports
    • helium target refilled, ready
  4. Today:
    • Production: 200nA, Al 10-4
  5. Run Plan
    • Production running
    • Beam studies planned for day shift on Monday
    • RF Recovery scheduled for Tuesday