Difference between revisions of "Run Planning Meeting Notes, Mar 29-Apr 4, 2018"

From GlueXWiki
Jump to: navigation, search
(Thursday, March 28 at 08:45)
Line 16: Line 16:
 
#* [https://logbooks.jlab.org/entry/3544635 CDC Background Studies] (Lubomir et al.)
 
#* [https://logbooks.jlab.org/entry/3544635 CDC Background Studies] (Lubomir et al.)
 
#* Converter thickness study (Alex S.)
 
#* Converter thickness study (Alex S.)
#* SSP Study (Alex S., maybe postpone to early next week)  
+
#* SSP Study (Alex S., postpone to early next week)  
 
#* Production running
 
#* Production running
 
# AOB
 
# AOB
Line 22: Line 22:
 
== Friday, March 29 at 08:45 ==
 
== Friday, March 29 at 08:45 ==
 
# Notes from the previous 24 hours:
 
# Notes from the previous 24 hours:
 +
#** Todd retuned Hall D beamline Thursday morning, considerable improvement
 +
#** Hovanes set diamond positions but didn't have time for spot adjustment, #1 today
 +
#** CDC background studies progressing or done
 
#* 0800 MCC meeting notes
 
#* 0800 MCC meeting notes
 
#* [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
 
#* [https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
Line 29: Line 32:
 
# Run Plan  
 
# Run Plan  
 
#* [https://halldweb.jlab.org/wiki/index.php/File:Spring18_week12.jpg Schematic]
 
#* [https://halldweb.jlab.org/wiki/index.php/File:Spring18_week12.jpg Schematic]
 +
#* Diamond spot adjustment (Hovanes)
 +
#* Converter thickness study (Alex S.)
 +
#* Production running
 
# AOB
 
# AOB

Revision as of 17:39, 29 March 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Thursday, March 28 at 08:45

  1. Notes from the previous 24 hours:
    • RF separator tested out ok, aimed to restore beam for swing shift but delayed due to CHL issues
    • Beam arrived just before midnight, convergence not good, owl shift spent tuning
    • 0800 MCC meeting notes - Todd retuning; planning machine work 4h Mon, 8h Tues MCC whiteboard
  2. Issues:
    • Shift-takers should at least log any acknowledged alarms so that they are not forgotten
    • Is there a how-to page for the BTA sheet? (load from epics, edit etc & guidelines on ABU/BANU)
  3. Reports:
  4. Run Plan
    • Re-establish Photon beam
    • 1h production to check beam quality & detectors
    • Diamond spot adjustment (Hovanes, needs to start before noon or try again tomorrow)
    • CDC Background Studies (Lubomir et al.)
    • Converter thickness study (Alex S.)
    • SSP Study (Alex S., postpone to early next week)
    • Production running
  5. AOB

Friday, March 29 at 08:45

  1. Notes from the previous 24 hours:
      • Todd retuned Hall D beamline Thursday morning, considerable improvement
      • Hovanes set diamond positions but didn't have time for spot adjustment, #1 today
      • CDC background studies progressing or done
    • 0800 MCC meeting notes
    • MCC whiteboard
  2. Issues:
  3. Reports:
  4. Run Plan
    • Schematic
    • Diamond spot adjustment (Hovanes)
    • Converter thickness study (Alex S.)
    • Production running
  5. AOB