! Shift  !! ABU !! BNA !! BANU  
 
! Shift  !! ABU !! BNA !! BANU  
 
|-
 
|-
|Day  || 6.49 || 0.63 || 0.88
+
|Day  || 6.49 || 0.88 || 0.63
 
|-
 
|-
|Swing || 6.97 || 0.32 || 0.71
+
|Swing || 6.97 || 0.71 || 0.32
 
|-
 
|-
|Owl  || 7.09 || 0.11 || 0.80
+
|Owl  || 7.09 || 0.80 || 0.11
 
|-
 
|-
|Total || 20.55 || 1.06 || 2.39
+
|Total || 20.55 || 2.39 || 1.06
 
|-
 
|-
 
|}
 
|}
Line 47: Line 47:
 
# Offline Analysis
 
# Offline Analysis
 
#* TAC runs?
 
#* TAC runs?
 +
# AOB
 +
 +
==Friday, March  3 ==
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 0.79 || 7.21 || 0.00
 +
|-
 +
|Swing || 4.75 || 2.50 || 0.75
 +
|-
 +
|Owl  || 6.83 || 1.09 || 0.08
 +
|-
 +
|Total || 12.37 || 10.80 || 0.83
 +
|-
 +
|}
 +
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Vacuum issues [~8 hours down]
 +
#* 1630 - Beam back
 +
#* 1730 - Attempt at trigger & DAQ studies
 +
#** 1800 to 1840 - ACC access to replace controller
 +
#** 1900 to 1930 - FSD Card swap
 +
#* 2000 - Start of production
 +
#** 500 - 20 min down due to cryomodule problems
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3464394 1] [https://logbooks.jlab.org/entry/3464486 2]
 +
# Hall-D/GlueX items
 +
#* Harp scans:  [https://logbooks.jlab.org/entry/3464169 Accel.], [https://logbooks.jlab.org/entry/3464184 Hall D], [https://logbooks.jlab.org/entry/3464277 Hovanes analysis]
 +
#* DAQ studies
 +
#* [https://logbooks.jlab.org/entry/3464181 MO phase drift] (Elton)
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: [r30920+] ~1250M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: B
 +
# Issues
 +
#* Red lines on run control GUI?
 +
#* Front-panel triggers off for 30920-2
 +
#* Firefox problems
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3464467 low-level report]
 +
#* Offline monitoring launch readiness
 +
# Run Plan
 +
#* Tagger/SC trigger
 +
#* Hall A Bleed-through?
 +
#* Empty target run?
 +
#* fADC250 Compressed Mode?
 +
#* Production
 +
#* Next week:
 +
#** High rate run [500 nA]
 +
#** Low rate run [50 nA + 2x10^-5 RL Al]
 +
# Offline Analysis
 +
#* TAC runs?
 +
# AOB
 +
 +
 +
==Saturday, March 4 ==
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 6.79 || 1.18 || 0.03
 +
|-
 +
|Swing || 6.17 || 0.71 || 1.12
 +
|-
 +
|Owl  || 7.29 || 0.64 || 0.07
 +
|-
 +
|Total || 20.25 || 2.53 || 1.22
 +
|-
 +
|}
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Steady beam delivery
 +
#* New slow lock status display [https://logbooks.jlab.org/entry/3464854 logbook entry]
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3464636 1] [https://logbooks.jlab.org/entry/3464733 2] [https://logbooks.jlab.org/entry/3464809 3]
 +
# Hall-D/GlueX items
 +
#* Tagger/SC trigger studies
 +
#* Hall A Bleed-through study: [https://logbooks.jlab.org/entry/3464633 1] [https://logbooks.jlab.org/entry/3464654 2]
 +
#* Empty target run accomplished
 +
#* fADC250 Compressed Mode Study
 +
#* Better downtime tracking in elog
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: 1771M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: 42.8B
 +
# Issues
 +
#* ~2hrs lost to DAQ problems on Fri. morning
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3464467 low-level report]
 +
# Run Plan
 +
#* Production + Afternoon harp scan
 +
#* Next week:
 +
#** High rate run [500 nA]
 +
#** Low rate run [50 nA + 2x10^-5 RL Al]
 +
# Offline Analysis
 +
#* [https://logbooks.jlab.org/entry/3464734 TPOL analysis update]
 +
#* TAC runs?
 +
# AOB
 +
 +
==Sunday, March 5 ==
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 6.94 || 0.74 || 0.32
 +
|-
 +
|Swing || 7.31 || 0.52 || 0.17
 +
|-
 +
|Owl  || 6.78 || 1.19 || 0.03
 +
|-
 +
|Total || 21.03 || 2.45 || 0.52
 +
|-
 +
|}
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Good beam during day & swing shifts, bumpy when changing currents
 +
#* [https://logbooks.jlab.org/entry/3465100 Work on slow locks at low current]
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3464909 1] [https://logbooks.jlab.org/entry/3464982 2] [https://logbooks.jlab.org/entry/3465091 3]
 +
# Hall-D/GlueX items
 +
#* Harp scan including beam dump radiator: [https://logbooks.jlab.org/entry/3464870 1], [https://logbooks.jlab.org/entry/3464879 2]
 +
#* [https://logbooks.jlab.org/entry/3465002 FCAL hole] - Bad board in ROCFCAL12, slot 18
 +
#* Low photon flux data taken during owl shift, ~14M triggers
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: 2338M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: 45.1B
 +
# Issues
 +
#* Bad FCAL fADC250, low on spares
 +
#* Known DAQ problems with EB/cMsg
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3465080 low-level report]
 +
# Run Plan
 +
#* Production Data
 +
#* Tentative Accelerator Schedule:
 +
#** Monday: Establish beam to Hall C - 9 AM to 1 PM
 +
#** Tuesday: Beam studies - 9 AM to 2+ PM
 +
# Offline Analysis
 +
#* TAC runs?
 +
# AOB
 +
 +
==Monday, March 6==
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 5.91 || 0.90 || 1.19
 +
|-
 +
|Swing || 7.25 || 0.66 || 0.09
 +
|-
 +
|Owl  || 7.00 || 0.87 || 0.13
 +
|-
 +
|Total || 20.16 || 2.43 || 1.41
 +
|}
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Steady beam delivery, resteer due to BLMs 1-2 per shift
 +
#* AC slow locks: [https://logbooks.jlab.org/entry/3465035 1], [https://logbooks.jlab.org/entry/3465100 2]
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3465285 1] [https://logbooks.jlab.org/entry/3465384 2]
 +
# Hall-D/GlueX items
 +
#* Busy Friday: min-bias trigger studies, Hall A Bleed-through study, fADC250 compressed mode, empty target run
 +
#** [https://logbooks.jlab.org/entry/3465388 Trigger studies]
 +
#** [https://logbooks.jlab.org/entry/3465391 Compressed mode for fadc250/125]
 +
#* Saturday: Harp scan including beam dump radiator: [https://logbooks.jlab.org/entry/3464870 1], [https://logbooks.jlab.org/entry/3464879 2]
 +
#* Sunday: Low photon flux data taken during owl shift, ~14M triggers
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: 2722M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: 47.8B
 +
# Issues
 +
#* [https://logbooks.jlab.org/entry/3465219 Bad fadc250, rocfcal12, slot 18]
 +
#* Known DAQ problems with live time, online monitoring reliability
 +
#** Rebooted gluon47 overnight
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3465368 low-level report]
 +
# Run Plan
 +
#* More Production Data
 +
#* High rate run [500 nA]?
 +
#** [[Spring 2017 High Intensity Run Plan]]
 +
#* Low rate run [50 nA + 2x10^-5 RL Al]?
 +
#** Halo counter settings
 +
#* New diamond alignment?
 +
#* Anything else?
 +
#** [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:_Spring_2017_Run#Runplan_time_charts Run progress]
 +
#* Tentative Accelerator Schedule:
 +
#** Monday: Establish beam to Hall C - 9 AM to 1 PM
 +
#** Tuesday: Beam studies - 9 AM to 2+ PM
 +
# Offline Analysis
 +
#* Calibration update
 +
#** [https://logbooks.jlab.org/entry/3464965 F1TDC Start Counter/Tagger study]
 +
#* Offline Monitoring update
 +
#* [https://logbooks.jlab.org/entry/3464734 TPOL analysis update]
 +
#* TAC runs?
 +
# AOB
 +
 +
==Tuesday, March 7==
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 1.16 || 6.80 || 0.01
 +
|-
 +
|Swing || 0.62 || 7.00 || 0.38
 +
|-
 +
|Owl  || 2.58 || 5.42 || 0.00
 +
|-
 +
|Total || 4.36 || 19.22 || 0.39
 +
|}
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Beam down until 8:15 PM, injector problems during day, problems delivering beam until ~5 AM
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3465563 1] [https://logbooks.jlab.org/entry/3465719 2]
 +
# Hall-D/GlueX items
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: 2.4M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: 50.2B
 +
# Issues
 +
#* [https://logbooks.jlab.org/entry/3465614 FDC noise studies]
 +
#* DAQ, online monitoring issues when restarting runs
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3465830 low-level report]
 +
# Run Plan
 +
#* Beam studies: 9 AM - 5 PM
 +
#** Hall D optics studies: 9 AM - 11 AM
 +
#** Controlled access at 11 AM
 +
#* [[Spring 2017 High Intensity Run Plan]]
 +
#* Full circuit with fADC250 compressed mode (4 diamond orientations and AMO)
 +
#* Harp scans with and without tagger quad
 +
#** [[Spring 2017 Harp scan plan]]
 +
#* L3 Tests?
 +
#* New diamond alignment?
 +
#* TAC run?
 +
#* [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:_Spring_2017_Run#Runplan_time_charts Run progress]
 +
# Offline Analysis
 +
#* Calibration update
 +
#* Offline Monitoring update
 +
#* [https://logbooks.jlab.org/entry/3464734 TPOL analysis update]
 +
#* TAC runs?
 +
# AOB
 +
 +
==Wednesday, March 8==
 +
 +
 +
{|border
 +
|-
 +
! Shift  !! ABU !! BNA !! BANU
 +
|-
 +
|Day  || 1.78 || 6.22 || 0.00
 +
|-
 +
|Swing || 1.73 || 6.21 || 0.03
 +
|-
 +
|Owl  || 6.29 || 1.40 || 0.31
 +
|-
 +
|Total || 9.80 || 13.83 || 0.34
 +
|}
 +
 +
 +
# Accelerator Status over the last 24 hrs
 +
#* Beam down until ~9:00 PM, problem cryomodule, overnight delivery to only Hall D
 +
#* Strip charts: [https://logbooks.jlab.org/entry/3466172 swing] [https://logbooks.jlab.org/entry/3466243 owl]
 +
# Hall-D/GlueX items
 +
#* Controlled Access
 +
#** TOF, FCAL, GEM
 +
#** Issues
 +
#* Harp scans
 +
#** Without tagger quad: [https://logbooks.jlab.org/entry/3466216 Accel.], [https://logbooks.jlab.org/entry/3466219 Rad.]
 +
#** With tagger quad: [https://logbooks.jlab.org/entry/3466234 Accel.], [https://logbooks.jlab.org/entry/3466226 Rad.]
 +
#* FADC250 firmware check [https://logbooks.jlab.org/entry/3466005 1], [https://logbooks.jlab.org/entry/3466149 2]
 +
#* [https://logbooks.jlab.org/entry/3466142 Low rate run study]
 +
#* In the last 24 hours:
 +
#** Total triggers collected during last period: 1006M
 +
#** Run Statistics [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1113040681 Spread Sheet]
 +
#** Current Total: 51.2B
 +
# Issues
 +
#* [https://logbooks.jlab.org/entry/3465998 Monitoring updates]
 +
#* FDC Noise studies: [https://logbooks.jlab.org/entry/3466017 1], [https://logbooks.jlab.org/entry/3466133 2]
 +
#* Firefox is slow
 +
# Monitoring
 +
#* [https://logbooks.jlab.org/entry/3465830 low-level report]
 +
# Run Plan
 +
#* Beam down until noon, support for Hall C KPP afterwards, other hall delivery not likely before owl (at best)
 +
#* Low current program
 +
#** Long-mode run
 +
#** Low-intensity run: 20 nA?  50 nA?
 +
#** L3 Tests?
 +
#** TAC run?
 +
#** Diamond alignment?
 +
#* [[Spring 2017 High Intensity Run Plan]] (archive)
 +
#* [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:_Spring_2017_Run#Runplan_time_charts Run progress]
 +
# Offline Analysis
 +
#* Calibration update
 +
#* Offline Monitoring update
 +
#* [https://logbooks.jlab.org/entry/3466035 Flux studies update]
 +
#* [https://logbooks.jlab.org/entry/3464734 TPOL analysis update]
 +
#* TAC runs?
 +
# New Run Coordinator: Richard Jones
 
# AOB
 
# AOB

Latest revision as of 09:34, 8 March 2017

<- Back to Run Coordination Meetings: Spring 2017 Run

Thursday, March 2

Shift ABU BNA BANU
Day 6.49 0.88 0.63
Swing 6.97 0.71 0.32
Owl 7.09 0.80 0.11
Total 20.55 2.39 1.06


  1. Accelerator Status over the last 24 hrs
  2. Hall-D/GlueX items
    • In the last 24 hours:
      • Production data taken after 10:30 AM Weds.
      • Long mode run
      • Black spots on diamonds
      • Total triggers collected during last period: 3099M
      • Run Statistics Spread Sheet
      • Current Total: 40.05B
  3. Issues
    • Problems with FCAL crate 9
    • FCAL red light issue
    • TRD gas issue
    • DAQ issues:
      • 5:42 - The DAQ keeps giving us "SEBO: Client has not reported for xx sec." errors, but then recovers after a minute. This happens every ~20mins or so. We will restart the DAQ again after the current run finishes.
      • ~22:00 - Monitoring stops working, have to start/stop runs several times to get events flowing through secondary ET
  4. Monitoring
  5. Run Plan
    • Production
    • Triggers: In-time random? Min-bias? FCAL+BCAL+ST?
  6. Offline Analysis
    • TAC runs?
  7. AOB

Friday, March 3

Shift ABU BNA BANU
Day 0.79 7.21 0.00
Swing 4.75 2.50 0.75
Owl 6.83 1.09 0.08
Total 12.37 10.80 0.83


  1. Accelerator Status over the last 24 hrs
    • Vacuum issues [~8 hours down]
    • 1630 - Beam back
    • 1730 - Attempt at trigger & DAQ studies
      • 1800 to 1840 - ACC access to replace controller
      • 1900 to 1930 - FSD Card swap
    • 2000 - Start of production
      • 500 - 20 min down due to cryomodule problems
    • Strip charts: 1 2
  2. Hall-D/GlueX items
  3. Issues
    • Red lines on run control GUI?
    • Front-panel triggers off for 30920-2
    • Firefox problems
  4. Monitoring
  5. Run Plan
    • Tagger/SC trigger
    • Hall A Bleed-through?
    • Empty target run?
    • fADC250 Compressed Mode?
    • Production
    • Next week:
      • High rate run [500 nA]
      • Low rate run [50 nA + 2x10^-5 RL Al]
  6. Offline Analysis
    • TAC runs?
  7. AOB


Saturday, March 4

Shift ABU BNA BANU
Day 6.79 1.18 0.03
Swing 6.17 0.71 1.12
Owl 7.29 0.64 0.07
Total 20.25 2.53 1.22
  1. Accelerator Status over the last 24 hrs
    • Steady beam delivery
    • New slow lock status display logbook entry
    • Strip charts: 1 2 3
  2. Hall-D/GlueX items
    • Tagger/SC trigger studies
    • Hall A Bleed-through study: 1 2
    • Empty target run accomplished
    • fADC250 Compressed Mode Study
    • Better downtime tracking in elog
    • In the last 24 hours:
      • Total triggers collected during last period: 1771M
      • Run Statistics Spread Sheet
      • Current Total: 42.8B
  3. Issues
    • ~2hrs lost to DAQ problems on Fri. morning
  4. Monitoring
  5. Run Plan
    • Production + Afternoon harp scan
    • Next week:
      • High rate run [500 nA]
      • Low rate run [50 nA + 2x10^-5 RL Al]
  6. Offline Analysis
  7. AOB

Sunday, March 5

Shift ABU BNA BANU
Day 6.94 0.74 0.32
Swing 7.31 0.52 0.17
Owl 6.78 1.19 0.03
Total 21.03 2.45 0.52
  1. Accelerator Status over the last 24 hrs
  2. Hall-D/GlueX items
    • Harp scan including beam dump radiator: 1, 2
    • FCAL hole - Bad board in ROCFCAL12, slot 18
    • Low photon flux data taken during owl shift, ~14M triggers
    • In the last 24 hours:
      • Total triggers collected during last period: 2338M
      • Run Statistics Spread Sheet
      • Current Total: 45.1B
  3. Issues
    • Bad FCAL fADC250, low on spares
    • Known DAQ problems with EB/cMsg
  4. Monitoring
  5. Run Plan
    • Production Data
    • Tentative Accelerator Schedule:
      • Monday: Establish beam to Hall C - 9 AM to 1 PM
      • Tuesday: Beam studies - 9 AM to 2+ PM
  6. Offline Analysis
    • TAC runs?
  7. AOB

Monday, March 6

Shift ABU BNA BANU
Day 5.91 0.90 1.19
Swing 7.25 0.66 0.09
Owl 7.00 0.87 0.13
Total 20.16 2.43 1.41
  1. Accelerator Status over the last 24 hrs
    • Steady beam delivery, resteer due to BLMs 1-2 per shift
    • AC slow locks: 1, 2
    • Strip charts: 1 2
  2. Hall-D/GlueX items
    • Busy Friday: min-bias trigger studies, Hall A Bleed-through study, fADC250 compressed mode, empty target run
    • Saturday: Harp scan including beam dump radiator: 1, 2
    • Sunday: Low photon flux data taken during owl shift, ~14M triggers
    • In the last 24 hours:
      • Total triggers collected during last period: 2722M
      • Run Statistics Spread Sheet
      • Current Total: 47.8B
  3. Issues
  4. Monitoring
  5. Run Plan
    • More Production Data
    • High rate run [500 nA]?
    • Low rate run [50 nA + 2x10^-5 RL Al]?
      • Halo counter settings
    • New diamond alignment?
    • Anything else?
    • Tentative Accelerator Schedule:
      • Monday: Establish beam to Hall C - 9 AM to 1 PM
      • Tuesday: Beam studies - 9 AM to 2+ PM
  6. Offline Analysis
  7. AOB

Tuesday, March 7

Shift ABU BNA BANU
Day 1.16 6.80 0.01
Swing 0.62 7.00 0.38
Owl 2.58 5.42 0.00
Total 4.36 19.22 0.39
  1. Accelerator Status over the last 24 hrs
    • Beam down until 8:15 PM, injector problems during day, problems delivering beam until ~5 AM
    • Strip charts: 1 2
  2. Hall-D/GlueX items
    • In the last 24 hours:
      • Total triggers collected during last period: 2.4M
      • Run Statistics Spread Sheet
      • Current Total: 50.2B
  3. Issues
  4. Monitoring
  5. Run Plan
  6. Offline Analysis
  7. AOB

Wednesday, March 8

Shift ABU BNA BANU
Day 1.78 6.22 0.00
Swing 1.73 6.21 0.03
Owl 6.29 1.40 0.31
Total 9.80 13.83 0.34


  1. Accelerator Status over the last 24 hrs
    • Beam down until ~9:00 PM, problem cryomodule, overnight delivery to only Hall D
    • Strip charts: swing owl
  2. Hall-D/GlueX items
    • Controlled Access
      • TOF, FCAL, GEM
      • Issues
    • Harp scans
    • FADC250 firmware check 1, 2
    • Low rate run study
    • In the last 24 hours:
      • Total triggers collected during last period: 1006M
      • Run Statistics Spread Sheet
      • Current Total: 51.2B
  3. Issues
  4. Monitoring
  5. Run Plan
    • Beam down until noon, support for Hall C KPP afterwards, other hall delivery not likely before owl (at best)
    • Low current program
      • Long-mode run
      • Low-intensity run: 20 nA? 50 nA?
      • L3 Tests?
      • TAC run?
      • Diamond alignment?
    • Spring 2017 High Intensity Run Plan (archive)
    • Run progress
  6. Offline Analysis
  7. New Run Coordinator: Richard Jones
  8. AOB