(Monday, Mar. 11 at 08:45)
Line 11: Line 11:
 
== Monday, Mar. 11 at 08:45 ==
 
== Monday, Mar. 11 at 08:45 ==
 
# Past 72 hours:
 
# Past 72 hours:
#* Beam restoration
+
#* Beam fully restored on Friday 2pm
 +
#** [https://logbooks.jlab.org/entry/3664823 Harp Scan]
 +
#** [https://logbooks.jlab.org/entry/3664864 AC Scan] unsuccessful due to beam position drifts, interrupted by spin dance
 +
#* Beam position drifts in y (AC:inner, 5C11B)  improved Saturday around noon after extraction lock was set, but still present
 +
#* CDC HV turned on Friday evening with nominal HV
 +
#** Included in DAQ Saturday, but no-field tracking prevents highlevel monitoring, [https://logbooks.jlab.org/entry/3665510 taken out again]
 +
#** Fix provided on Sunday (thanks Simon),  but rootspy has to be updated
 +
#* [https://logbooks.jlab.org/entry/3665911 Trigger studies] Saturday evening (Sasha)
 
# Issues:
 
# Issues:
 +
#* ComCal temperature and humidity: [https://logbooks.jlab.org/entry/3665534] [https://logbooks.jlab.org/entry/3665646]
 +
#* ComCal Voltage Alarm [https://logbooks.jlab.org/entry/3666037][[https://logbooks.jlab.org/entry/3666074], needs rapid access (Hovanes)
 
# Reports
 
# Reports
# Today (Monday): Beam Studies
+
#* [https://logbooks.jlab.org/entry/3666057 Rates after energy change] (Alexandre)
#* Access: Tim, ...
+
#* Online monitoring
 +
# Plans:
 +
#* Today: Beam studies cancelled
 +
#* Tuesday: RF recovery cancelled
 
#* Resume production
 
#* Resume production
 
  
 
== Friday, Mar. 8 at 08:45 ==
 
== Friday, Mar. 8 at 08:45 ==

Revision as of 08:32, 11 March 2019


Monday, Mar. 11 at 08:45

  1. Past 72 hours:
    • Beam fully restored on Friday 2pm
      • Harp Scan
      • AC Scan unsuccessful due to beam position drifts, interrupted by spin dance
    • Beam position drifts in y (AC:inner, 5C11B) improved Saturday around noon after extraction lock was set, but still present
    • CDC HV turned on Friday evening with nominal HV
      • Included in DAQ Saturday, but no-field tracking prevents highlevel monitoring, taken out again
      • Fix provided on Sunday (thanks Simon), but rootspy has to be updated
    • Trigger studies Saturday evening (Sasha)
  2. Issues:
    • ComCal temperature and humidity: [1] [2]
    • ComCal Voltage Alarm [3][[4], needs rapid access (Hovanes)
  3. Reports
  4. Plans:
    • Today: Beam studies cancelled
    • Tuesday: RF recovery cancelled
    • Resume production

Friday, Mar. 8 at 08:45

  1. Past 24 hours:
  2. Issues:
  3. Reports
  4. Today (Friday):
    • Collimator scan (Hovanes)
    • Trigger studies? (Sasha)
    • Production: 200nA, Al 10-4

Thursday, Mar. 7 at 08:45

  1. Past 24 hours:
  2. Issues
  3. Reports:
  4. Today (Thursday):
    • Walk-Through (Elton)
    • Lock up (noon?)
    • Swing shift on standby
    • Accelerator restoration progressing, 11.2GeV beam expected during owl shift
    • Beam restoration, step 1 (Hovanes)
    • Empty target run?