Difference between revisions of "Run Planning Meeting Notes, March 15 - March 22, 2023"

From GlueXWiki
Jump to: navigation, search
(Plans on Accelerator Side)
(Plans)
Line 41: Line 41:
 
** As soon as they leave, put Hall D back in Power Permit and request beam restoration
 
** As soon as they leave, put Hall D back in Power Permit and request beam restoration
 
** Start off with new harp scans, then continue production
 
** Start off with new harp scans, then continue production
* Straight-track run ~50nA (Magnetic field off: drift chamber)[March 19th Sunday swing][Justin, Sasha, Lubomir, Naomi][Access not required]
+
* Straight-track run ~50nA
 +
** planned for March 19th Sunday swing
 +
** magnetic field ramped down
 +
** access not required
 +
** people to contact: Justin, Sasha, Lubomir, Naomi
 +
 
 
==Plans on Accelerator Side==
 
==Plans on Accelerator Side==
 
* Hall C running continues, no apparent issues that might interrupt them before Monday
 
* Hall C running continues, no apparent issues that might interrupt them before Monday

Revision as of 08:38, 16 March 2023

Zoom Connect Meeting ID: 160 199 0060 / Passcode 8394 MCC Whiteboard Hall D counting room white board Spreadsheet with list of runs Integrated Trigger Count Hall D Logbook

Thursday March 16

Past 24 hours

  • Tagger Hall Access (March 15) by Hovanes(After the Hall is surveyed and gets into controlled access)
  • High current run(900 nA)[High intensity scan:Final round] with modified trigger thresh-holds[Wednesday swing/Thursday day Shift][Justin, Sasha, Lubomir, Naomi][Access not required]

Shift Reports

Reports

Issues

Plans

  • Continue running production
  • Visitors tour of Hall D starts at 4:45pm 3/16
    • Data collection should end sometime after 4:00pm, when convenient before 4:20
    • Contact MCC and ask to drop Hall D to RESTRICTED, tagger hall not affected
    • Ask them to contact RADCON to sweep Hall D for the visit
    • Visit should end by 6:45pm
    • As soon as they leave, put Hall D back in Power Permit and request beam restoration
    • Start off with new harp scans, then continue production
  • Straight-track run ~50nA
    • planned for March 19th Sunday swing
    • magnetic field ramped down
    • access not required
    • people to contact: Justin, Sasha, Lubomir, Naomi

Plans on Accelerator Side

  • Hall C running continues, no apparent issues that might interrupt them before Monday

Regular Production Cycle

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 3 runs PERP (0/90) (one additional run per cycle for next 2 cycles, to catch up with PARA 0/90 -RTJ)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)