Difference between revisions of "Run Planning Meeting Notes, May 2-May 6, 2018"

From GlueXWiki
Jump to: navigation, search
(Friday, May 4 at 08:45)
(Thursday, May 3 at 08:45)
Line 36: Line 36:
 
#Issues:
 
#Issues:
 
# Reports:
 
# Reports:
#* Yields w/o W foil: [https://logbooks.jlab.org/entry/3571261]
+
#* ρ yields w/o W foil: [https://logbooks.jlab.org/entry/3571261]
 
# Run Plan
 
# Run Plan
 
#*Thursday/Friday
 
#*Thursday/Friday

Revision as of 15:39, 3 May 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Friday, May 4 at 08:45

  1. Notes from the previous 24 hours:
    • Network problems on accelerator site, CHL1 trip, RF recovery, Hall A pass change
    • Beam back expected at 8pm
    • Harp Scan
    • Raw mode run
    • Production running
  2. Issues:
  3. Reports:
    • ω yields w/o W foil [1]
  4. Run Plan
    • Friday
      • Fast raster scan (9am, 60min)
      • TAC run (10am, 1 shift)
    • Saturday
      • Production
    • Sunday
      • 5am end of physics, 6am end of run, restricted access from 10am
    • Week 17
  5. AOB

Thursday, May 3 at 08:45

  1. Notes from the previous 24 hours:
    • RF Recovery and Tour: scheduled from 9:00-15:00, but RF recovery estimated until 17:00
    • Planned Hall A pass change (several h)
    • Network problems on accelerator site: [2][3][4]
    • Harp Scan
    • Production running
  2. Issues:
  3. Reports:
    • ρ yields w/o W foil: [5]
  4. Run Plan
    • Thursday/Friday
      • Raw mode run
      • Fast raster scan (9am, 60min)
      • TAC run (10am, 1 shift)
    • Saturday
      • Production
    • Sunday
      • 5am end of physics, 6am end of run
    • Week 17
  5. AOB