Difference between revisions of "Run Planning Meeting Notes, Nov 1-Nov 8, 2018"

From GlueXWiki
Jump to: navigation, search
(Tuesday, Nov 6 at 08:45)
(Wednesday, Nov 7 at 08:45)
 
(19 intermediate revisions by 2 users not shown)
Line 9: Line 9:
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week7.jpg Hall D schedule for week 7]
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week7.jpg Hall D schedule for week 7]
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week8.jpg Hall D schedule for week 8]
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week8.jpg Hall D schedule for week 8]
 +
*[https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet]
  
 +
== Wednesday, Nov 7 at 08:45 ==
 +
# Last 24h:
 +
#*Recovery studies 0830-1300 ish
 +
#*Steady production running until the same pump failed again at around 11pm
 +
#*Rough night - resumed running at 6am, thanks to Keith Blackburn who replaced main and backup pumps
 +
#*[https://logbooks.jlab.org/entry/3621941 CCAL work continued]
 +
#*[https://logbooks.jlab.org/entry/3621853 Hovanes reinstated the beamline vacuum alarm auto-notifications]
 +
#*Harp scans [https://logbooks.jlab.org/entry/3621428 Mon pm][https://logbooks.jlab.org/entry/3622081 Tues pm]
 +
#*[https://logbooks.jlab.org/entry/3622387 Rates]
 +
#*TagH monitoring [https://logbooks.jlab.org/entry/3621890 fixed, thanks to David]
 +
#*The gas shed is much less scary now - thanks, Tim!
 +
#Issues
 +
#*[https://logbooks.jlab.org/entry/3622012 More trouble with the same vacuum pump] Tim & Mark made access to power-cycle it, have replacement parts ready for use if needed. 
 +
#Reports
 +
#*Monitoring
 +
# Plans
 +
#*Sasha proposes to take one TAC run at low PS field (400 A) today (Wed) and postpone the nominal field TAC run (910A) until immediately after the low energy measurement programme.  This is partly for convenience (5h/run) and partly because we already have some TAC data with the nominal PS field.
 +
#*After the TAC run, we need to check transmission w AC position before starting low Eg measurements
 +
#Notes
 +
#*Today: After TAC run: AC transmission check; Harp scans after TAC run, consider focus adjustments then eg Jay's one quad setting
 +
#*Then start low Eg programme with amo https://halldweb.jlab.org/wiki-private/index.php/2018_Low_energy_measurements
 +
#*css_new (just a reminder)
  
 
== Tuesday, Nov 6 at 08:45 ==
 
== Tuesday, Nov 6 at 08:45 ==
Line 15: Line 38:
 
#*Beam studies 0830-1410 [https://logbooks.jlab.org/entry/3621340 CompCAL work continued][https://logbooks.jlab.org/entry/3621363 Cables & pulser]
 
#*Beam studies 0830-1410 [https://logbooks.jlab.org/entry/3621340 CompCAL work continued][https://logbooks.jlab.org/entry/3621363 Cables & pulser]
 
#*[https://logbooks.jlab.org/entry/3621324 Target compressor cooling water valve adjusted and alarm re-enabled]   
 
#*[https://logbooks.jlab.org/entry/3621324 Target compressor cooling water valve adjusted and alarm re-enabled]   
 +
#*[https://logbooks.jlab.org/entry/3621549 Vacuum pump in the tagger hall suffered a control board failure] [https://logbooks.jlab.org/entry/3621616 Mark saved the day]. Found a replacement CB & made it work again. 3.5h UED.
 +
#*Owl shift pretty smooth.  Trips but nothing long-lasting.
 
#*[https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet]
 
#*[https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet]
 
#Issues
 
#Issues
 +
#*[https://logbooks.jlab.org/entry/3621616 major alarm did not call mechanical on call phone]
 +
#*The runs immediately before and after the pump shutdown were taken while the pressure changed in the beamline - noted in shift summary.
 +
#*[https://logbooks.jlab.org/entry/3621650 TagH monitoring]
 +
#*The gas shed contains many big spiders, the web strands are disturbing
 
#Reports
 
#Reports
 +
#*[https://logbooks.jlab.org/entry/3621810 Monitoring]
 +
#*[https://logbooks.jlab.org/entry/3621216 rates over the weekend][https://logbooks.jlab.org/entry/3620794 Sat pm harp scan] [https://logbooks.jlab.org/entry/3621428 Mon pm harp scans]
 
# Plans
 
# Plans
 
#*Tues system recovery ~ 4h
 
#*Tues system recovery ~ 4h
 
#**Access for CCAL work
 
#**Access for CCAL work
 
#**Carl Bolitho needs to reboot a Hall D tagger switch halld-t1-7-sw during the access
 
#**Carl Bolitho needs to reboot a Hall D tagger switch halld-t1-7-sw during the access
#*Wed: V-wire TAC runs with coherent peak at 9 and then 7 GeV, check transmission w AC position, then low Eg measurements start
+
#*Wed: V-wire TAC runs with nominal PS current (910 A) and PS current at 400 A for low energy measurements.  Then check transmission w AC position and start low Eg measurements
 
#Notes
 
#Notes
 +
#*css_new
 +
#*Vacuum pump speed alarm re-enabled by Hovanes
  
 
== Monday, Nov 5 at 08:45 ==
 
== Monday, Nov 5 at 08:45 ==

Latest revision as of 10:45, 7 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run

Wednesday, Nov 7 at 08:45

  1. Last 24h:
  2. Issues
  3. Reports
    • Monitoring
  4. Plans
    • Sasha proposes to take one TAC run at low PS field (400 A) today (Wed) and postpone the nominal field TAC run (910A) until immediately after the low energy measurement programme. This is partly for convenience (5h/run) and partly because we already have some TAC data with the nominal PS field.
    • After the TAC run, we need to check transmission w AC position before starting low Eg measurements
  5. Notes

Tuesday, Nov 6 at 08:45

  1. Last 24h:
  2. Issues
  3. Reports
  4. Plans
    • Tues system recovery ~ 4h
      • Access for CCAL work
      • Carl Bolitho needs to reboot a Hall D tagger switch halld-t1-7-sw during the access
    • Wed: V-wire TAC runs with nominal PS current (910 A) and PS current at 400 A for low energy measurements. Then check transmission w AC position and start low Eg measurements
  5. Notes
    • css_new
    • Vacuum pump speed alarm re-enabled by Hovanes

Monday, Nov 5 at 08:45

  1. Notes from Friday & weekend:
    • Friday
      • Email from PD that the recovery time on Tuesday will probably only be 4h.
      • Sasha started work on PS field studies at 2pm (from 1pm to 2pm mostly no beam). Will return later or tomorrow to finish these.
      • ComCAL humidity sensor alarmed, Sasha Nick & Vlad made a short access to deal with this, found the sensor was bad.
      • Hovanes found new best collimator x from beam scan.
      • Found Jay's suggested quadrupole change improved focus slightly, keeping with that
      • Overnight: good production running
    • Saturday
      • Smooth running continued until 2pm cryo temp trouble, down for 4h
      • Sasha looked at CCAL trigger during downtime and finished up the PS field studies (with beam)
      • Overnight: mostly smooth production running. Time-travel went without a hitch (transition to DST).
    • Sunday
      • RF issues ~8am, 4h down + some shorter outages
      • Swing shift more steady, overnight MCC quad problem 1.5h, otherwise ok
    • Trigger Spreadsheet
  2. Issues
  3. Reports
  4. Plans
  5. Notes
    • css_new is an option Only now I remember this
    • Low E measurements to go ahead after TAC runs on Wed.

Friday, Nov 2 at 08:45

  1. Last 24h
    • active collimator scan done. The intention was to make sure that the beam was centered on the collimator and then decide whether to ask for beam convergence adjustment but the results were confusing and we decided to continue running without changes for now.
    • Mark filled both alcohol bubblers
    • Sasha looked at BCAL LED trigger timing - hopefully this is fixed
    • Production - beam trips quite frequent
    • Cleared up some mysteries from yesterday - a network issue was the cause of the beamline counters switching off. It should have triggered an alarm but didn't. And the TagM mess was indeed when the DAQ config was set to cosmics.
  2. Issues
  3. Reports
  4. Plans
    • Production
    • Monday beam studies 0830, ~ 4h ; Tues recovery ~ 8h
    • Tentative plan for V-wire TAC run on Wed next week at 2 PS settings, nominal & lower Eg. Then follow with low Eg test runs. Maybe a 3rd TAC run after the low E data-taking.
    • Q on whether to go ahead w second set of 7GeV test runs - need collaboration agreement
    • Remember to make a plan for the clocks changing on Sunday
    • Schedule for week 7
    • Acc whiteboard
    • Counting house whiteboard
  5. AOB
  6. Notes from this meeting:
    • Hovanes to try scan in x of beam position on AC today
    • Follow that with Jay's suggestion & harp scan. Checked w Todd & Mike M - ok.
    • Sasha to do test run w PS at lower field today
    • Mon & Tues downtime to be used for CCAL installation. Controlled access should be ok.
    • Discuss 7GeV run plans more on Monday
    • Tim will adjust target compressor cooling water valve on Monday - should be ok until then. Chris & Alexandre see all the alarms.

Thursday, Nov 1 at 08:45

  1. Last 24h
  2. Issues
  3. Reports
  4. Plans
  5. AOB
    • Notes from today's meeting: Hovanes to scan AC early pm.
    • Shifters to call Sasha if beam goes off for >= 1h during weekend daytime, to check BCAL LED trigger diffs between up & down and long & short modes
    • Sasha said shift crew should not use the cosmic trigger at all. Use production trigger even if only to collect cosmics during a long down-time.
    • Tentative plan for V-wire TAC run on Wed next week at 2 PS settings, nominal & lower Eg. Then follow with low Eg test runs. Maybe a 3rd TAC run after the low E data-taking.
    • Q on whether to go ahead w second set of 7GeV test runs - need collaboration agreement
    • Remember to make a plan for the clocks changing on Sunday