(Thursday, Nov 15 at 08:45)
(Thursday, Nov 15 at 08:45)
Line 27: Line 27:
 
#* TAC run this morning/afternoon. With V-wire
 
#* TAC run this morning/afternoon. With V-wire
 
#* Production running
 
#* Production running
 +
#Discussion ComCal commissioning
 +
#* [ runplan (V.3)]
 +
#* [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11], [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12], [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13]
 
#Notes
 
#Notes

Revision as of 08:07, 15 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run


Thursday, Nov 15 at 08:45

  1. Last 24h:
    • Standard production running
  2. Issues
  3. Reports
    • [ Monitoring] (Thomas)
  4. Plans
    • TAC run this morning/afternoon. With V-wire
    • Production running
  5. Discussion ComCal commissioning
  6. Notes