(Tuesday, Nov 20 at 08:45)
(Tuesday, Nov 20 at 08:45)
Line 28: Line 28:
 
#Plans
 
#Plans
 
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week]
 
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week]
#*<font color="red"><b>[https://docs.google.com/spreadsheets/d/1UT3o4yJ-avlIQzmZKJo2nRrgVPzYKJvGPJ0oqAn81Oo/edit?usp=sharing Luminosity study] </b></font>J. Stevens
+
#*<font color="red"><b>Luminosity study. [https://docs.google.com/spreadsheets/d/1UT3o4yJ-avlIQzmZKJo2nRrgVPzYKJvGPJ0oqAn81Oo/edit?usp=sharing Plan] </b></font>J. Stevens
 
#* Standard production running
 
#* Standard production running
 
#Discussion ComCal commissioning
 
#Discussion ComCal commissioning

Revision as of 09:32, 20 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run


Tuesday, Nov 20 at 08:45

  1. Last 24h:
    • FCal HV scan (A. Somov)
    • 2pm-6pm: optic optimization (T. Satogata)
    • Standard production running
  2. Issues
    • Optic tuning unsuccessful: background on our Harp scan 100 times larger and some of the tagger radiation monitors have twice larger signals. Scrapping is likely the cause. MCC backed-out of the new optics. Harp background and radiation monitor signals back to normal. Transmission back to the same as Monday morning (still 15% lower than at the start of the month).
    • Coherent peak shape (Beni)
  3. Reports
  4. Plans
  5. Discussion ComCal commissioning
  6. Notes

Monday, Nov 19 at 08:45

  1. Last 72h:
    • Friday Morning: Optic optimization
    • TAC run (Alexander S.)
    • Empty target run+ raw mode run
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Time chart for this week
    • 30 min FCal scan (A. Somov)
    • 2pm: optic optimization (T. Satogata)
    • Standard production running
  5. Discussion ComCal commissioning
  6. Notes

Friday, Nov 16 at 08:45

  1. Last 24h:
    • Check V-wire rate in preparation for TAC on Friday. (Alexander S.)
    • Check issue with CBrem gui. It appears to be gone (Hovanes)
    • Maintenance: 1pm-4/5pm.
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Time chart for this week
    • Optics adjustment (Todd/Jay) 30 min.
    • TAC run this morning/afternoon.
    • Standard production running over the week end.
  5. Discussion ComCal commissioning
  6. Notes
    • No meetings this week end.

Thursday, Nov 15 at 08:45

  1. Last 24h:
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Monday maintenance is moved to today, 1pm-4/5pm.
    • Check V-wire position wrt beam (Sacha).
    • Investigate issue with CBrem gui. Meanwhile, fill the target.
    • Production running, starting with amorphous (for CBrem ref.)
    • Optics adjustment (Todd/Jay) 30 min.
      • Access to move back the flux monitor
      • Other access?
    • TAC run this morning/afternoon is postponed.
    • Optics adjustment (Todd/Jay) 30 min.
  5. Discussion ComCal commissioning
  6. Notes